  1. (a)A railroad must certify in the response plan that it reviewed the NCP (40 CFR part 300) and that its response plan is consistent with the NCP.
  2. (b)At a minimum, for consistency with the NCP, a comprehensive response plan must include all of the following:
    1. (1)Demonstrate a railroad's clear understanding of the Incident Command System and Unified Command and the roles and responsibilities of the Federal On-Scene Coordinator;
    2. (2)Include procedures to immediately notify the National Response Center; and
    3. (3)Establish provisions to ensure safety at the response site.