  1. (a)A railroad must certify for each response zone that it reviewed each applicable ACP (or Regional Contingency Plan (RCP) for areas lacking an ACP).
  2. (b)At a minimum, for consistency with the applicable ACP (or Regional Contingency Plan (RCP) for areas lacking an ACP), the comprehensive response plan must do all of the following:
    1. (1)Address the removal of a worst-case discharge, and the mitigation or prevention of the substantial threat of a worst-case discharge, of oil;
    2. (2)Identify environmentally sensitive or significant areas along the route, as defined in § 130.5, which could be adversely affected by a worst-case discharge, by reviewing and summarizing the applicable ACP or RCP;
    3. (3)Incorporate appropriate strategies identified in applicable ACPs or RCPs, to protect environmentally sensitive or significant areas identified in paragraph (b)(2) of this section;
    4. (4)Describe the responsibilities of the railroad and of Federal, State, and local agencies in removing a discharge and in mitigating or preventing a substantial threat of a discharge; and
    5. (5)Identify the procedures to obtain any required Federal and State authorization for using alternative response strategies such as in-situ burning and/or chemical agents, as provided for in the applicable ACP and subpart J of 40 CFR part 300.