49 CFR §192.503
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)No person may operate a new segment of pipeline, or return to service a segment of pipeline that has been relocated or replaced, until—
- (b)The test medium must be liquid, air, natural gas, or inert gas that is—
- (c)Except as provided in § 192.505(a), if air, natural gas, or inert gas is used as the test medium, the following maximum hoop stress limitations apply:
- (d)Each joint used to tie in a test segment of pipeline is excepted from the specific test requirements of this subpart, but each non-welded joint must be leak tested at not less than its operating pressure.
- (e)If a component other than pipe is the only item being replaced or added to a pipeline, a strength test after installation is not required, if the manufacturer of the component certifies that:
- (1)The component was tested to at least the pressure required for the pipeline to which it is being added;
- (2)The component was manufactured under a quality control system that ensures that each item manufactured is at least equal in strength to a prototype and that the prototype was tested to at least the pressure required for the pipeline to which it is being added; or
- (3)The component carries a pressure rating established through applicable ASME/ANSI, Manufacturers Standardization Society of the Valve and Fittings Industry, Inc. (MSS) specifications, or by unit strength calculations as described in § 192.143.