49 CFR §194.7
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)An operator of a pipeline for which a response plan is required under § 194.101, may not handle, store, or transport oil in that pipeline unless the operator has submitted a response plan meeting the requirements of this part.
- (b)An operator must operate its onshore pipeline facilities in accordance with the applicable response plan.
- (c)The operator of a pipeline line section described in § 194.103(c), may continue to operate the pipeline for two years after the date of submission of a response plan, pending approval or disapproval of that plan, only if the operator has submitted the certification required by § 194.119(e).