49 CFR §195.262
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Adequate ventilation must be provided in pump station buildings to prevent the accumulation of hazardous vapors. Warning devices must be installed to warn of the presence of hazardous vapors in the pumping station building.
- (b)The following must be provided in each pump station:
- (c)Each safety device must be tested under conditions approximating actual operations and found to function properly before the pumping station may be used.
- (d)Except for offshore pipelines, pumping equipment must be installed on property that is under the control of the operator and at least 15.2 m (50 ft) from the boundary of the pump station.
- (e)Adequate fire protection must be installed at each pump station. If the fire protection system installed requires the use of pumps, motive power must be provided for those pumps that is separate from the power that operates the station.