49 CFR §195.50
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
An accident report is required for each failure in a pipeline system subject to this part in which there is a release of the hazardous liquid or carbon dioxide transported resulting in any of the following:
- (a)Explosion or fire not intentionally set by the operator.
- (b)Release of 5 gallons (19 liters) or more of hazardous liquid or carbon dioxide, except that no report is required for a release of less than 5 barrels (0.8 cubic meters) resulting from a pipeline maintenance activity if the release is:
- (c)Death of any person;
- (d)Personal injury necessitating hospitalization;
- (e)Estimated property damage, including cost of clean-up and recovery, value of lost product, and damage to the property of the operator or others, or both, exceeding $50,000.