49 CFR §350.215
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)First year of the CVSP.
- (1)FMCSA will notify the Lead State Agency within 30 days after FMCSA begins its review of the State's first year of the CVSP, including the budget, whether FMCSA:
- (2)If FMCSA withholds approval of the CVSP, FMCSA will give the Lead State Agency a written explanation of the reasons for withholding approval and allow the Lead State Agency to modify and resubmit the CVSP for approval.
- (3)The Lead State Agency will have 30 days from the date of the notice under paragraph (a)(2) of this section to modify and resubmit the CVSP.
- (4)Failure to resubmit the modified CVSP may delay funding or jeopardize MCSAP eligibility.
- (5)Final disapproval of a resubmitted CVSP will result in disqualification for MCSAP funding for that fiscal year.
- (b)Annual update for the second or third year of the CVSP.
- (1)FMCSA will notify the Lead State Agency within 30 days after FMCSA begins its review of the State's annual update, including the budget, whether FMCSA:
- (2)If FMCSA withholds approval of the annual update, FMCSA will give the Lead State Agency a written explanation of the reasons for withholding approval and allow the Lead State Agency to modify and resubmit the annual update for approval.
- (3)The Lead State Agency will have 30 days from the date of the notice under paragraph (b)(2) of this section to modify and resubmit the annual update.
- (4)Failure to resubmit the modified annual update may delay funding or jeopardize MCSAP eligibility.
- (5)Final disapproval of a resubmitted annual update will result in disqualification for MCSAP funding for that fiscal year.
- (c)Judicial review. Any State aggrieved by an adverse decision under this section may seek judicial review under 5 U.S.C. chapter 7.