50 CFR §86.15
Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov ↗
- (a)Dredging in this part includes the physical action of removing sediment from the basin and any associated actions, such as engineering, permitting, dredge-material management, and other actions or costs that occur because of the dredging. Dredging can qualify as an eligible action under the grant only if the costs for the dredging-related actions do not exceed $200,000.
- (b)When you complete the project, the BIG-funded dredged area must:
- (c)You must show in the grant application that:
- (d)You certify by signing the grant application that you have enough resources to maintain the dredged area at the approved width and depth for the useful life of the BIG-funded facility, under typical conditions.