StacksVerified U.S. regulatory reference

7 CFR §3430.1205

Verified against eCFR.gov as of June 20, 2026View official text on eCFR.gov
  1. (a)Construction. Funds made available for grants under this subpart shall not be used for the construction of a new building or facility or the acquisition, expansion, remodeling, or alteration of an existing building or facility, including site grading and improvement, and architect fees.
  2. (b)Indirect costs. Subject to § 3430.54, indirect costs are allowable for Education, Extension and Training grants. For Rural Practice Enhancement grants, indirect costs are not allowable; however, overhead costs may be requested, not to exceed 50 percent of the award.