(a)
(2) In this section, the term "defense acquisition authority" means the Secretary of a military department or the commander of the United States Special Operations Command.
(b)
(1) The milestone schedule for the development of the major defense acquisition program, including the scheduled dates for low-rate initial production, initial operational capability, full-rate production, and full operational capability and the date as of when the replacement system is scheduled to assume the majority of responsibility for the mission of the existing system.
(2) An analysis of the existing system to assess the following:
(A) Anticipated funding levels necessary to—
(i) ensure acceptable reliability and availability rates for the existing system; and
(ii) maintain mission capability of the existing system against the relevant threats.
(B) The extent to which it is necessary and appropriate to—
(i) transfer mature technologies from the new system or other systems to enhance the mission capability of the existing system against relevant threats; and
(ii) provide interoperability with the new system during the period from initial fielding until the new system assumes the majority of responsibility for the mission of the existing system.
(c)
(1) the existing system is no longer relevant to the mission;
(2) the mission has been eliminated;
(3) the mission has been consolidated with another mission in such a manner that another existing system can adequately meet the mission requirements; or
(4) the duration of time until the new system assumes the majority of responsibility for the existing system's mission is sufficiently short so that mission availability, capability, interoperability, and force protection requirements are maintained.
(d)
Prior Provisions
A prior section 2437, added Pub. L. 99–500, §101(c) [title X, §906(a)(1)], Oct. 18, 1986, 100 Stat. 1783–82, 1783–135, and Pub. L. 99–591, §101(c) [title X, §906(a)(1)], Oct. 30, 1986, 100 Stat. 3341–82, 3341–135; Pub. L. 99–661, div. A, title IX, formerly title IV, §906(a)(1), Nov. 14, 1986, 100 Stat. 3915; renumbered title IX, Pub. L. 100–26, §3(5), Apr. 21, 1987, 101 Stat. 273; amended Pub. L. 100–26, §7(b)(8), Apr. 21, 1987, 101 Stat. 280; Pub. L. 100–180, div. A, title VIII, §803(b), Dec. 4, 1987, 101 Stat. 1125; Pub. L. 100–224, §5(a)(3), Dec. 30, 1987, 101 Stat. 1538, related to designation of defense enterprise programs for milestone authorization, prior to repeal by Pub. L. 103–160, div. A, title VIII, §821(a)(5), Nov. 30, 1993, 107 Stat. 1704.
Effective Date
Pub. L. 108–375, div. A, title VIII, §805(b), Oct. 28, 2004, 118 Stat. 2009, provided that: "Section 2437 of title 10, United States Code, as added by subsection (a), shall apply with respect to a major defense acquisition program for a system that is under development as of the date of the enactment of this Act [Oct. 28, 2004] and is not expected to reach initial operational capability before October 1, 2008. The Secretary of Defense shall require that a sustainment plan under that section be developed not later than one year after the date of the enactment of this Act for the existing system that the system under development is intended to replace."