(a)
(1) the acquisition of the facility satisfies the requirements of the military department concerned for the authorized military construction project; and
(2) it is in the best interests of the United States to acquire the facility instead of carrying out the authorized military construction project.
(b)
(2) The costs of anticipated modifications, repairs, or conversions under paragraph (1) are required to remain within the authorized amount of the military construction project. The Secretary concerned shall consider such costs in determining whether the acquisition of an existing facility is—
(A) more cost effective than carrying out the authorized military construction project; and
(B) in the best interests of the United States.
(c)
Amendments
2017—Subsec. (c). Pub. L. 115–91 substituted "notifies the appropriate committees of Congress" for "transmits to the appropriate committees of Congress a written notification" and "14-day period" for "21-day period" and struck out "or, if earlier, the end of the 14-day period beginning on the date on which a copy of the report is provided" after "received by the committees".
2006—Subsec. (c). Pub. L. 109–163 substituted "21-day period" for "30-day period" and "14-day period" for "21-day period".
2003—Subsec. (c). Pub. L. 108–136 struck out "the end of the 30-day period beginning on the date" after "until" and inserted last sentence.
1996—Subsec. (c). Pub. L. 104–106 substituted "appropriate committees of Congress" for "Committees on Armed Services and the Committees on Appropriations of the Senate and House of Representatives".
Effective Date
Pub. L. 103–160, div. B, title XXVIII, §2805(b), Nov. 30, 1993, 107 Stat. 1887, provided that: "Section 2813 of title 10, United States Code, as added by subsection (a), shall apply with respect to military construction projects authorized on or after the date of the enactment of this Act [Nov. 30, 1993]."