(a)
(b)
(2) The Secretary of Defense shall include in each notification submitted under paragraph (1) the following information:
(A) In the case of a military construction project for energy conservation, the justification and current cost estimate for the project, the expected savings-to-investment ratio, simple payback estimates, and the project's measurement and verification cost estimate.
(B) In the case of a military construction project for energy resilience or energy security, the rationale for how the project would enhance mission assurance, support mission critical functions, and address known vulnerabilities.
(c)
(1) The title, location, a brief description of the scope of work, the original project cost estimate, and the current working cost estimate.
(2) In the case of a military construction project for energy conservation—
(A) the original expected savings-to-investment ratio and simple payback estimates and measurement and verification cost estimate;
(B) the most current expected savings-to-investment ratio and simple payback estimates and measurement and verification plan and costs; and
(C) a brief description of the measurement and verification plan and planned funding source.
(3) In the case of a military construction project for energy resilience or energy security, the rationale for how the project would enhance mission assurance, support mission critical functions, and address known vulnerabilities.
(4) Such other information as the Secretary considers appropriate.
Amendments
2018—Pub. L. 115–232 substituted "resilience" for "resiliency" in section catchline.
2017—Pub. L. 115–91, §2831(c)(1), substituted "energy resilience" for "energy resiliency" wherever appearing in text.
Subsec. (b)(1). Pub. L. 115–91, §2801(e)(1), struck out "in writing" after "shall notify" and "or, if earlier, the end of the 14-day period beginning on the date on which a copy of the notification is provided" after "received by such committees" and substituted "14-day period" for "21-day period".
2016—Pub. L. 114–328, §2805(a)(1)(A), inserted "resiliency and" before "conservation construction projects" in section catchline. Text quoted in directory language of amendment was editorially conformed to the style of the catchline.
Subsec. (a). Pub. L. 114–328, §2805(a)(1)(B), substituted "military construction project for energy resiliency, energy security, or energy conservation" for "military construction project for energy conservation".
Subsec. (b). Pub. L. 114–328, §2805(b)(1)(A), designated existing provisions as par. (1) and added par. (2).
Subsec. (c). Pub. L. 114–328, §2805(b)(2), added subsec. (c).
Effective Date of 2016 Amendment
Pub. L. 114–328, div. B, title XXVIII, §2805(b)(1)(B), Dec. 23, 2016, 130 Stat. 2714, provided that: "The amendment made by subparagraph (A) [amending this section] shall apply with respect to notifications provided during fiscal year 2017 or any succeeding fiscal year."