Follow-on requirement or contract. The determination of whether a particular requirement or contract is a follow-on includes consideration of whether the scope has changed significantly, requiring meaningful different types of work or different capabilities; whether the magnitude or value of the requirement has changed by at least 25 percent for equivalent periods of performance; and whether the end user of the requirement has changed. As a general guide, if the procurement satisfies at least one of these three conditions, it may be considered a new requirement. However, meeting any one of these conditions is not dispositive that a requirement is new. In particular, the 25 percent rule cannot be applied rigidly in all cases. Conversely, if the requirement satisfies none of these conditions, it is considered a follow-on procurement.
* * * * *