(b) Competition prior to offer and acceptance. The procuring activity competed a requirement among 8(a) Participants prior to offering the requirement to SBA and did not clearly evidence its intent to conduct an 8(a) competitive acquisition.
* * * * *
(c) * * *
(4) SBA does not typically consider the value of a bridge contract when determining whether an offered procurement is a new requirement. A bridge contract is meant to be a temporary stop-gap measure intended to ensure the continuation of service while an agency finalizes a long-term procurement approach.
(d) Release for non-8(a) or limited 8(a) competition.
(1) Except as set forth in paragraph (d)(4) of this section, where a procurement is awarded as an 8(a) contract, its follow-on requirement must remain in the 8(a) BD program unless SBA agrees to release it for non-8(a) competition. Where a procurement will contain work currently performed under one or more 8(a) contracts, and the procuring agency determines that the procurement should not be considered a follow-on requirement to the 8(a) contract(s), the procuring agency must notify SBA that it intends to procure such specified work outside the 8(a) BD program through a requirement that it considers to be new. Additionally, a procuring agency must notify SBA where it seeks to reprocure a follow-on requirement through a pre-existing limited contracting vehicle which is not available to all 8(a) BD Program Participants and the previous/current 8(a) award was not so limited. If a procuring agency would like to fulfill a follow-on requirement outside of the 8(a) BD program, it must make a written request to and receive the concurrence of the AA/BD to do so. In determining whether to release a requirement from the 8(a) BD program, SBA will consider:
* * * * *
(4) The requirement that a follow-on procurement must be released from the 8(a) BD program in order for it to be fulfilled outside the 8(a) BD program does not apply:
(i) Where previous orders were offered to and accepted for the 8(a) BD program pursuant to §124.503(i)(2); or
(ii) Where a procuring agency will use a mandatory source (see FAR Subparts 8.6 and 8.7(48 CFR subparts 8.6 and 8.7)). In such a case, the procuring agency should notify SBA at least 30 days prior to the end of the contract or order.