(b) * * *
(2) * * *
(ii) Designating a small business as the managing venturer of the joint venture, and designating a named employee of the small business managing venturer as the manager with ultimate responsibility for performance of the contract (the “Responsible Manager”).
(A) The managing venturer is responsible for controlling the day-to-day management and administration of the contractual performance of the joint venture, but other partners to the joint venture may participate in all corporate governance activities and decisions of the joint venture as is commercially customary.
(B) The individual identified as the Responsible Manager of the joint venture need not be an employee of the small business at the time the joint venture submits an offer, but, if he or she is not, there must be a signed letter of intent that the individual commits to be employed by the small business if the joint venture is the successful offeror. The individual identified as the Responsible Manager cannot be employed by the mentor and become an employee of the small business for purposes of performance under the joint venture.
(C) Although the joint venture managers responsible for orders issued under an IDIQ contract need not be employees of the protégé, those managers must report to and be supervised by the joint venture's Responsible Manager;
* * * * *
(iv) Stating that the small business participant(s) must receive profits from the joint venture commensurate with the work performed by them, or a percentage agreed to by the parties to the joint venture whereby the small business participant(s) receive profits from the joint venture that exceed the percentage commensurate with the work performed by them, and that at the conclusion of the joint venture contract(s) and/or the termination of a joint venture, any funds remaining in the joint venture bank account shall distributed at the discretion of the joint venture members according to percentage of ownership;
(v) * * * This account must require the signature or consent of all parties to the joint venture for any payments made by the joint venture to its members for services performed. * * *
* * * * *
(xi) Stating that annual performance-of-work statements required by paragraph (h)(1) must be submitted to SBA and the relevant contracting officer not later than 45 days after each operating year of the joint venture; and
(xii) Stating that the project-end performance-of-work required by paragraph (h)(2) must be submitted to SBA and the relevant contracting officer no later than 90 days after completion of the contract.
* * * * *
(c) * * *
(1) * * * Except as set forth in paragraph (c)(4) of this section, the 40% calculation for protégé workshare follows the same rules as those set forth in §125.6 concerning supplies, construction, and mixed contracts, including the exclusion of the same costs from the limitation on subcontracting calculation (e.g., cost of materials excluded from the calculation in construction contracts).
* * * * *
(4) Work performed by a similarly situated entity will not count toward the requirement that a protégé must perform at least 40% of the work performed by a joint venture.
* * * * *
(e) Capabilities, past performance and experience. When evaluating the capabilities, past performance, experience, business systems and certifications of an entity submitting an offer for a contract set aside or reserved for small business as a joint venture established pursuant to this section, a procuring activity must consider work done and qualifications held individually by each partner to the joint venture as well as any work done by the joint venture itself previously. A procuring activity may not require the protégé firm to individually meet the same evaluation or responsibility criteria as that required of other offerors generally. The partners to the joint venture in the aggregate must demonstrate the past performance, experience, business systems and certifications necessary to perform the contract.
* * * * *
(h) * * *
(2) At the completion of every contract set aside or reserved for small business that is awarded to a joint venture between a protégé small business and a mentor authorized by §125.9, and upon request by SBA or the relevant contracting officer, the small business partner to the joint venture must submit a report to the relevant contracting officer and to SBA, signed by an authorized official of each partner to the joint venture, explaining how and certifying that the performance of work requirements were met for the contract, and further certifying that the contract was performed in accordance with the provisions of the joint venture agreement that are required under paragraph (b) of this section.
* * * * *