15 CFR Supplement No. 2 to Part 714
Deadlines for Submission of Schedule 3 Declarations, Reports, and Amendments
April 14, 2021
Open Table
Declarations | Applicable forms | Due dates |
---|---|---|
Annual Declaration on Past Activities (previous calendar year)—Declared plant site (production) | Certification, 3-1, 3-2, 3-3 (if also exported or imported), A (as appropriate), B (optional) | February 28 of the year following any calendar year in which the production of a Schedule 3 chemical exceeded the declaration threshold in §714.1(a)(1)(i) of the CWCR. |
Annual Report on Exports and Imports (previous calendar year)—Plant site, trading company, other persons | Certification, 3-1, 3-3.3 and 3-3.4, A (as appropriate), B (optional) | February 28 of the year following any calendar year in which exports or imports of a Schedule 3 chemical by a plant site, trading company, or other person subject to the CWCR (as described in §714.2(a) of the CWCR) exceeded the threshold in §714.2(a) of the CWCR. |
Combined Declaration & Report | Certification, 3-1, 3-2, and 3-3, A (as appropriate), B (optional) | February 28 of the year following any calendar year in which the production of a Schedule 3 chemical and the export or import of the same or a different Schedule 3 chemical by a declared plant site exceeded the applicable thresholds in §§714.1(a)(1)(i) and 714.2(a), respectively, of the CWCR. |
Annual Declaration on Anticipated Activities (Production) (next calendar year) | Certification, 3-1, 3-2, 3-3.2, A (as appropriate), B (optional) | September 3 of the year prior to any calendar year in which Schedule 3 production is anticipated to occur. |
Declaration on Additionally Planned Activities | Certification, 3-1, 3-3.1 and 3-3.2, A (as appropriate), B (optional) | 15 calendar days before the additionally planned activity begins. |
Amended Declaration | Certification, 3-1, 3-2, 3-3 | |
—Declaration information | —15 calendar days after change in information. | |
—Company information | —30 calendar days after change in information. | |
—Post-inspection letter | —45 calendar days after receipt of letter. | |
Amended Report | Certification, 3-1, 3-2, 3-3, A (as appropriate), B (optional) | —15 calendar days after change in information. |
Amended Combined Declaration & Report | Certification, 3-1, 3-2, 3-3, A (as appropriate), B (optional) | —15 calendar days after change in information. |