(a) The CPSC may deny an application for any of the following reasons:
(1) Failure to complete all information, and/or attestations, and/or failure to provide accompanying documentation, required in connection with an application within 30 days after notice of a deficiency by the CPSC;
(2) Submission of false or misleading information concerning a material fact(s) on an application, any materials accompanying an application, or on any other information provided to the CPSC related to a third party conformity assessment body's ability to become or to remain a CPSC-accepted third party conformity assessment body; or
(3) Failure to satisfy necessary requirements described in §1112.13, such as ISO/IEC 17025:2005(E) accreditation by a ILAC-MRA signatory accreditation body for the CPSC scope for which acceptance of accreditation is being sought.
(b) The CPSC's denial of an application will follow the process described in §1112.51.