(a)
(1)
(i) Activation of COOP and suspension of Commission operations. The Commission's Continuity of Operations Plan may be activated by the Chairman (or the Chairman's delegate pursuant to §376.205, as appropriate). In circumstances in which the Commission's Continuity of Operations Plan is activated, Commission headquarters operations may be temporarily disrupted in whole or in part or communications with Commission headquarters may be temporarily unavailable, either of which may prevent the public or the Commission from meeting regulatory or statutory requirements. After the Commission's Continuity of Operations Plan is activated, Commission operations other than emergency functions may be suspended in whole or in part by the Chairman (or the Chairman's delegate, as appropriate). The provisions of this section are effective upon activation of the Continuity of Operations Plan and the subsequent suspension of Commission operations, in whole or in part, and shall remain in effect up to 30 days, or such shorter time than 30 days as the Chairman (or the Chairman's delegate, as appropriate) determines to be appropriate, or such longer time than 30 days as the Commission (or the Commission's delegate pursuant to section 376.204 of this Part, as appropriate) determines to be appropriate. Resumption of Commission operations following activation of the Continuity of Operations Plan and any subsequent suspension of Commission operations, in whole or in part, may occur either simultaneously for all activities, or over time for just some activities, and in such manner and at such time, as the Chairman (or the Chairman's delegate, as appropriate) or the Commission (or the Commission's delegate, as appropriate) determines to be appropriate.
(ii) Notification of COOP activation and, following such activation, notification of suspension of Commission operations. During periods when the Commission's Continuity of Operations Plan is activated and, following such activation, when Commission operations are subsequently suspended in whole or in part, the Chairman (or the Chairman's delegate pursuant to §376.205, as appropriate) will notify the public that the Continuity of Operations Plan has been activated and that Commission operations have been suspended in whole or in part by sending a press release announcing that fact to major wire services, industry press, and appropriate metropolitan area radio stations The Commission's Web site (http://www.ferc.gov) or the Commission's alternative Web site (http://www.fercalt.gov), as appropriate, will be activated and a notice that the Continuity of Operations Plan has been activated and that Commission operations have been suspended in whole or in part will be prominently displayed thereon. The Web site or alternative Web site, as appropriate, will act as a resource for the press, industry, and general public. An additional press release will be sent to appropriate media outlets and a notice will be prominently displayed on the Commission's Web site or alternative Web site, as appropriate, when the Continuity of Operations Plan is deactivated and the Commission's headquarters are reopened or reconstituted and Commission operations resume.
(2) Activities continued during COOP. Notwithstanding other provisions of this section, during periods when the Commission's Continuity of Operations Plan is activated and, following such activation, when Commission operations are subsequently suspended in whole or in part, the Commission will continue to conduct emergency functions. As part of its emergency functions, the Commission will act on requests to ensure continued construction of essential natural gas facilities with sensitive construction timelines, on Commencement of Service requests, and on completion of dam safety work, in a manner consistent with the maintenance of environmental protections. Also as part of its emergency functions, the Commission will ensure that its personnel are available to respond to plant accidents or reportable incidents at LNG facilities, and to address dam safety, public safety, and security incidents at jurisdictional hydropower projects and to address other matters involving the safety of human life or protection of property. Alternate channels of communication will include measures to ensure that these activities can go forward unhindered.
(b) Standards of conduct for transmission service providers. During periods when the Commission's Continuity of Operations Plan is activated and, following such activation, when Commission operations are suspended in whole or in relevant part, a Transmission Provider affected by the same emergency affecting the Commission may, for up to 30 days, or such other time as the Chairman (or the Chairman's delegate pursuant to §376.205, as appropriate) may direct, delay compliance with the requirement to report to the Commission each emergency that resulted in any deviation from the standards of conduct within 24 hours of such deviation. If the emergency prevents such Transmission Provider from posting information on its OASIS or Internet Web site, the Transmission Provider may, for up to 30 days, or such shorter time as the Chairman (or the Chairman's delegate, as appropriate) may direct or such longer time as the Commission (or the Commission's delegate pursuant to §376.204, as appropriate) may direct, also delay compliance with the requirements of §358.4(a)(2) of this chapter to post this information on its OASIS or Internet Web site, as applicable.
(c) Tolling of time periods for Commission action. Unless otherwise directed, for those pending matters where the date that the Commission must act falls during the period when the Continuity of Operations Plan is activated and, following such activation, when Commission operations are suspended in whole or in relevant part and also during the 14 days thereafter, the Commission tolls, for purposes of further consideration, the time period in which the Commission must act. Such matters include:
(1) 60-day period to act on requests for Exempt Wholesale Generator or Foreign Utility Company status;
(2) 90-day period for acting on requests for certification of qualifying facility status;
(3) 60-day period for acting on interlocking directorate applications;
(4) 60-day period for acting on Public Utility Holding Company Act exemptions and waivers;
(5) 180-period for acting on applications under section 203 of the Federal Power Act;
(6) 150-day period for acting on intrastate pipeline applications for approval of proposed rates;
(7) Period ending 60 days prior to the Electric Reliability Organization's (ERO) fiscal year for acting on the ERO's budget;
(8) 60-day period for acting on notifications that a Reliability Standard may conflict with a function, rule, order, tariff, rate schedule or agreement;
(9) 60-day period for acting on applications for review of a penalty imposed by the ERO for violation of a Reliability Standard;
(10) 45-day protest period for protesting Prior Notice Filings, and the 30-day period for resolving and filing to withdraw such Protests;
(11) 30-day period for acting on requests for rehearing;
(12) Time periods for action by a presiding officer or the Motions Commissioner, as well as by the Commission, on motions to permit interlocutory appeals, interlocutory appeals and certified questions; and
(13) 90-day period for acting on applications requesting relief from, or reinstatement of, an electric utility's mandatory purchase obligation pursuant to section 210(m) of the Public Utility Regulatory Policies Act of 1978.
(d) Suspension of certain requirements. Unless otherwise directed, during periods when the Commission's Continuity of Operations Plan is activated and, following such activation, when Commission operations are suspended in whole or in relevant part, the requirements to file by a certain date are suspended when communications with Commission headquarters are unavailable such that filings, submissions, and notifications cannot be received by the Commission. Unless otherwise directed by the Chairman (or the Chairman's delegate pursuant to §376.205, as appropriate), those filings, submissions, and notifications, the filing of which was suspended, will be due the first day that communications with Commission headquarters are available such that filings, submissions, and notifications can be received by the Commission. Such filings, submissions, and notifications include:
(1) Filings to comply with orders or notices, including orders or notices issued by the Commission, a presiding officer, and a Commission decisional employee (including the directors of the Commission's various offices and their delegates);
(2) Filings required to be made by a date certain either under the Commission's regulations, or under orders and notices issued by the Commission, a presiding officer, and a Commission decisional employee (including the directors of the Commission's various offices and their delegates); such filings include, e.g., briefs, motions, and answers to motions;
(3) Motions to intervene and notices of intervention, or protests;
(4) Comments responding to notices of inquiry, proposed rulemakings or technical conferences;
(5) Responses to data requests and deficiency letters issued either by the Commission or by a decisional employee pursuant to delegated authority;
(6) Self-reports of violations;
(7) Responses to staff audit reports;
(8) Contacts with the Commission's Enforcement Hotline;
(9) Accounting filings required by the Commission's Uniform Systems of Accounts;
(10) Forms required to be filed by a date certain;
(11) Notices of intent to file new applications and applications for new licenses pursuant to section 15 of the Federal Power Act;
(12) Requests for rehearing of orders and letter orders issued either by the Commission or by a decisional employee pursuant to delegated authority; and
(13) The Electric Reliability Organization's advising the Commission of the Electric Reliability Organization's intent to issue Level 1 Advisories, Level 2 Recommendations, and Level 3 Essential Actions, and the Electric Reliability Organization's reporting to the Commission on actions taken in response to Level 2 Recommendations and Level 3 Essential Actions.
(e) Acceptance and suspension of rate and other filings. Unless otherwise directed, if the date by which the Commission is required to act on rate and other filings made pursuant to section 4 of the Natural Gas Act, section 205 of the Federal Power Act, and section 6(3) of the Interstate Commerce Act falls during a period when the Continuity of Operations Plan is activated and, following such activation, when Commission operations are suspended in whole or in relevant part and also during the 14 days thereafter, such filings shall be deemed to be accepted for filing and suspended and made effective on the requested effective date, subject to refund and further order of the Commission. The acceptance for filing and suspension of these filings is without prejudice to any further action the Commission may take with respect to these filings.
(f) Electric Reliability Organization penalties. Unless otherwise directed, if the date a penalty imposed by the Electric Reliability Organization under section 215 of the Federal Power Act would take effect falls during a period when the Continuity of Operations Plan is activated and, following such activation, when Commission operations are suspended in whole or in relevant part and also during the 14 days thereafter, review of such penalty by the Commission shall be deemed to be initiated and the penalty shall be stayed pending further action of the Commission.
(g) Consistency of State action with Reliability Standard. Unless otherwise directed, if the date by which a Commission determination under section 215 of the Federal Power Act as to whether a State action is inconsistent with a Reliability Standard is required to be made falls during a period when the Continuity of Operations Plan is activated and, following such activation, when Commission operations are suspended in whole or in relevant part and also during the 14 days thereafter, the effectiveness of the State action will be deemed to be stayed pending further action by the Commission.
(h) Suspension of evidentiary hearings and related conferences and meetings. During periods when the Continuity of Operations Plan is activated and, following such activation, when Commission operations are suspended in whole or in relevant part, all evidentiary hearings, prehearing conferences, settlement conferences, and other meetings before presiding officers are suspended, and any requirement that a presiding officer act on motions (including motions to permit interlocutory appeals and to certify questions) is also suspended. Service of data requests and other discovery, and responses thereto, by and to the Commission's Trial Staff is similarly suspended. Upon resumption of Commission operations in whole or in relevant part, such hearings, conferences and other meetings will be rescheduled, action on motions also will be rescheduled, and service of data requests and other discovery, and responses thereto, by and to the Commission's Trial Staff, will similarly be rescheduled, by the presiding officer or the Commission, as appropriate.
(i) Enforcement Actions under the Public Utility Regulatory Policies Act of 1978. Unless otherwise directed, if the date by which the Commission is required to act on a petition for enforcement action under section 210(h)(2) of the Public Utility Regulatory Policies Act of 1978 falls during a period when the Continuity of Operations Plan is activated and, following such activation, when Commission operations are suspended in whole or in relevant part, and also during the 14 days thereafter, the Commission will not initiate such an enforcement action under section 210(h)(2) of the Public Utility Regulatory Policies Act of 1978 and the petitioner may itself bring its own enforcement action in the appropriate court.
(j) Chairman's and Commission's authority to modify deadlines and timeframes. During periods when the Continuity of Operations Plan is activated and, following such activation, when Commission operations are suspended in whole or in part and also during the 14 days thereafter, the Chairman (or the Chairman's delegate pursuant to §376.205, as appropriate), may shorten, and the Commission (or the Commission's delegate pursuant to §376.204, as appropriate) may extend, with respect to the matters addressed in this section, as appropriate:
(1) The time periods and dates for filings with the Commission, a decisional employee, or a presiding officer;
(2) The time periods and dates for reports, submissions and notifications to the Commission, a decisional employee, or a presiding officer; and
(3) The time periods and dates for actions by the Commission, a decisional employee, or a presiding officer.
[Order 765, 77 FR 43490, July 25, 2012]