You may consider including the following items in any phase-one solicitation:
(a) The scope of work;
(b) The phase-one evaluation factors and their relative weights, including:
(1) Technical approach (but not detailed design or technical information);
(2) Technical qualifications, such as—
(i) Specialized experience and technical competence;
(ii) Capability to perform (including key personnel); and
(iii) Past performance of the members of the offeror's team (including the architect-engineer and construction members);
(3) Other appropriate factors (excluding cost or price related factors, which are not permitted in phase-one);
(c) Phase-two evaluation factors; and
(d) A statement of the maximum number of offerors that will be short listed to submit phase-two proposals.