(a) Serial numbers of homes completed on-site. The serial number of each home completed in conformance with this section must include the prefix or suffix “SC”.
(b) Labeling. A manufacturer that has received a DAPIA approval under §3282.604 may certify and label a manufactured home that is substantially completed in the manufacturer's plant at the proper completion of the in-plant production phase, even though some aspects of construction will be completed on-site in accordance with the DAPIA's approval. Any such homes or sections of such homes must have a label affixed in accordance with §3282.362(c)(2) and be shipped with a Consumer Information Notice that meets the requirements of §3282.606.
(c) Site inspection. Prior to occupancy, the manufacturer must ensure that each home is inspected on-site. The manufacturer is responsible for inspecting all aspects of construction that are completed on-site as provided in its approved designs and quality assurance manual for on-site completion.
(d) Site inspection report.
(1) In preparing the site inspection report, the manufacturer must use the inspection checklist approved by the DAPIA in accordance with §3282.603(d)(9), and must prepare a final site inspection report and provide a copy to the IPIA within 5 business days of completing the report. Within 5 business days after the date that the IPIA notifies the manufacturer of the IPIA's approval of the final site inspection report, the manufacturer must provide a copy of the approved report to the lessor or purchaser prior to occupancy and, as applicable, the appropriate retailer and any person or entity other than the manufacturer that performed the on-site construction work.
(2) Each approved final site inspection report must include:
(i) The name and address of the manufacturer;
(ii) The serial number of the manufactured home;
(iii) The address of the home site;
(iv) The name of the person and/or agency responsible for the manufacturer's final site inspection;
(v) The name of each person and/or agency who performs on-site inspections on behalf of the IPIA, the name of the person responsible for acceptance of the manufacturer's final on-site inspection report on behalf of the IPIA, and the IPIA's name, mailing address, and telephone number;
(vi) A description of the work performed on-site and the inspections made;
(vii) When applicable, verification that any problems noted during inspections have been corrected prior to certification of compliance; and
(viii) Certification by the manufacturer of completion in accordance with the DAPIA-approved instructions and that the home conforms with the approved design or, as appropriate under §3282.362(a)(1)(iii), the construction and safety standards.
(3) The IPIA must review each manufacturer's final on-site inspection report and determine whether to accept that inspection report.
(i) Concurrent with the manufacturer's final site inspection, the IPIA or the IPIA's agent must inspect all of the on-site work for homes completed using an approval under this section. The IPIA must use the inspection checklist approved by the DAPIA in accordance with §3282.603(d)(9).
(ii) If the IPIA determines that the manufacturer is not performing adequately in conformance with the approval, the IPIA must redtag and reinspect until it is satisfied that the manufacturer is conforming to the conditions included in the approval. The home may not be occupied until the manufacturer and the IPIA have provided reports, required by this section, confirming compliance with the Construction and Safety Standards.
(iii) The IPIA must notify the manufacturer of the IPIA's acceptance of the manufacturer's final site inspection report. The IPIA may indicate acceptance by issuing its own final site inspection report or by indicating, in writing, its acceptance of the manufacturer's site inspection report showing that the work completed on-site is in compliance with the DAPIA approval and the Construction and Safety Standards.
(4) Within 5 business days of the date of IPIA's notification to the manufacturer of the acceptance of its final site inspection report, the manufacturer must provide to the purchaser or lessor, as applicable, the manufacturer's final site inspection report. For purposes of establishing the manufacturer's and retailer's responsibilities under the Act and subparts F and I of this part, the sale or lease of the manufactured home will not be considered complete until the purchaser or lessor, as applicable, has been provided with the report.
(e) Report to HUD.
(1) The manufacturer must report to HUD through its IPIA, on the manufacturer's monthly production report required in accordance with §3282.552, the serial number and site completion numeric identification (see §3282.603(d)(1)) of each home produced under an approval issued pursuant to this section.
(2) The report must be consistent with the DAPIA approval issued pursuant to this section.
(3) The manufacturer must submit a copy of the report, or a separate listing of all information provided on each report for homes that are completed under an approval issued pursuant to this section, to the SAAs of the States where the home is substantially completed in the factory and where the home is sited, as applicable.