30 CFR § 250.1753
After I decommission a pipeline, what information must I submit?
July 29, 2020
Within 30 days after you decommission a pipeline, you must submit a written report to the Regional Supervisor that includes the following:
(a) A summary of the decommissioning operation including the date it was completed;
(b) A description of any mitigation measures you took; and
(c) A statement signed by your authorized representative that certifies that the pipeline was decommissioned according to the approved application.