You must notify the appropriate BSEE District Manager when you successfully complete or recomplete a well for production. You must:

(a) Notify the District Manager within 5 working days of placing the well in a production status. You must confirm oral notification by telefax or e-mail within those 5 working days.

(b) Provide the following information in your notification:

(1) Lessee or operator name;

(2) Well number, lease number, and OCS area and block designations;

(3) Date you placed the well on production (indicate whether or not this is first production on the lease);

(4) Type of production; and

(5) Measured depth of the production interval.


Tried the LawStack mobile app?

Join thousands and try LawStack mobile for FREE today.

  • Carry the law offline, wherever you go.
  • Download CFR, USC, rules, and state law to your mobile device.