You must include the following information in your DWOP:

(a) A description and schematic of the typical wellbore, casing, and completion;

(b) Structural design, fabrication, and installation information for each surface system, including host facilities;

(c) Design, fabrication, and installation information on the mooring systems for each surface system;

(d) Information on any active stationkeeping system(s) involving thrusters or other means of propulsion used with a surface system;

(e) Information concerning the drilling and completion systems;

(f) Design and fabrication information for each riser system (e.g., drilling, workover, production, and injection);

(g) Pipeline information;

(h) Information about the design, fabrication, and operation of an offtake system for transferring produced hydrocarbons to a transport vessel;

(i) Information about subsea wells and associated systems that constitute all or part of a single project development covered by the DWOP;

(j) Flow schematics and Safety Analysis Function Evaluation (SAFE) charts (API RP 14C, subsection 4.3c, incorporated by reference in §250.198) of the production system from the Surface Controlled Subsurface Safety Valve (SCSSV) downstream to the first item of separation equipment;

(k) A description of the surface/subsea safety system and emergency support systems to include a table that depicts what valves will close, at what times, and for what events or reasons;

(l) A general description of the operating procedures, including a table summarizing the curtailment of production and offloading based on operational considerations;

(m) A description of the facility installation and commissioning procedure;

(n) A discussion of any new technology that affects hydrocarbon recovery systems;

(o) A list of any alternate compliance procedures or departures for which you anticipate requesting approval;

(p) If you propose to use a pipeline free standing hybrid riser (FSHR) on a permanent installation that utilizes a buoyancy air can suspended from the top of the riser, you must provide the following information in your DWOP in the discussions required by paragraphs (f) and (g) of this section:

(1) A detailed description and drawings of the FSHR, buoy, and the associated connection system;

(2) Detailed information regarding the system used to connect the FSHR to the buoyancy air can, and associated redundancies; and

(3) Descriptions of your monitoring system and monitoring plan to monitor the pipeline FSHR and the associated connection system for fatigue, stress, and any other abnormal condition (e.g., corrosion) that may negatively impact the riser system's integrity.

(q) Payment of the service fee listed in §250.125.

[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 26017, Apr. 29, 2016; 84 FR 21973, May 15, 2019]