(a) The Director may direct the suspension or temporary prohibition of production or any other operation or activity on all or any part of a lease when it has been determined that such suspension or temporary prohibition is in the National interest to:
(1) Facilitate proper development of a lease including a reasonable time to develop a mine and construct necessary support facilities, or
(2) Allow for the construction or negotiation for use of transportation facilities.
(b) The Director may also direct or, at the request of the lessee, approve a suspension or temporary prohibition of production or any other operation or activity, if:
(1) The lessee failed to comply with a provision of applicable law, regulation, order, or the lease;
(2) There is a threat of serious, irreparable, or immediate harm or damage to life (including fish and other aquatic life), property, any mineral deposit, or the marine, coastal, or human environment;
(3) The suspension or temporary prohibition is in the interest of National security or defense;
(4) The suspension or temporary prohibition is necessary for the initiation and conduct of an environmental evaluation to define mitigation measures to avoid or minimize adverse environmental impacts.
(5) The suspension or temporary prohibition is necessary to facilitate the installation of equipment necessary for safety of operations and protection of the environment;
(6) The suspension or temporary prohibition is necessary to allow for undue delays encountered by the lessee in obtaining required permits or consents, including administrative or judicial challenges or appeals;
(7) The Director determines that continued operations would result in premature abandonment of a producing mine, resulting in the loss of otherwise recoverable OCS minerals;
(8) The Director determines that the lessee cannot successfully operate a producing mine due to market conditions that are either temporary in nature or require temporary shutdown and reinvestment in order for the lessee to adapt to the conditions; or
(9) The suspension or temporary prohibition is necessary to comply with judicial decrees prohibiting production or any other operation or activity, or the permitting of those activities, effective the date set by the court for that prohibition.
(c) When the Director orders or approves a suspension or a temporary prohibition of operation or activity including production on all of a lease pursuant to paragraph (a) or (b) of this section, the term of the lease shall be extended for a period of time equal to the period of time that the suspension or temporary prohibition is in effect, except that no lease shall be so extended when the suspension or temporary prohibition is the result of the lessee's gross negligence or willful violation of a provision of the lease or governing regulations.
(d) The Director may, at any time within the period prescribed for a suspension or temporary prohibition issued pursuant to paragraph (b)(2) of this section, require the lessee to submit a Delineation, Testing, or Mining Plan to the Bureau of Ocean Energy Management for approval in accordance with the requirements for the approval of such plans in part 582 of this title.
(e)
(1) When the Director orders or issues a suspension or a temporary prohibition pursuant to paragraph (b)(2) of this section, the Director may require the lessee to conduct site-specific studies to identify and evaluate the cause(s) of the hazard(s) generating the suspension or temporary prohibition, the potential for damage from the hazard(s), and the measures available for mitigating the hazard(s). The nature, scope, and content of any study shall be subject to approval by the Director. The lessee shall furnish copies and all results of any such study to the Director. The cost of the study shall be borne by the lessee unless the Director arranges for the cost of the study to be borne by a party other than the lessee. The Director shall make results of any such study available to interested parties and to the public as soon as practicable after the completion of the study and submission of the results thereof.
(2) When the Director determines that measures are necessary, on the basis of the results of the studies conducted in accordance with paragraph (e)(1) of this section and other information available to and identified by the Director, the lessee will be required to take appropriate measures to mitigate, avoid, or minimize the damage or potential damage on which the suspension or temporary prohibition is based. In choosing between alternative mitigation measures, the Director will balance the cost of the required measures against the reduction or potential reduction in damage or threat of damage or harm to life (including fish and other aquatic life), to property, to any mineral deposits (in areas leased or not leased), to the National security or defense, or to the marine, coastal, or human environment. When deemed appropriate by the Director, the lessee must submit to the Bureau of Ocean Energy Management a revised Delineation, Testing, or Mining Plan that incorporates the mitigation measures required by the Director.
(f)
(1) If under the provisions of paragraphs (b)(2), (3), and (4) of this section, the Director, with respect to any lease, directs the suspension of production or other operations on the entire leasehold, no payment of rental or minimum royalty shall be due for or during the period of the directed suspension and the time for the lessee specify royalty free period of a period of reduced royalty pursuant to 30 CFR 581.28(b) will be extended for the period of directed suspension. If under the provisions of paragraphs (b)(2), (3), and (4) of this section the Director, with respect to a lease on which there has been no production, directs the suspension of operations on the entire leasehold, no payment of rental shall be due during the period of the directed suspension.
(2) If under the provisions of this section, the Director grants the request of a lessee for a suspension of production or other operations, the lessee's obligations to pay rental, minimum royalty, or royalty shall continue to apply during the period of the approved suspension, unless the Director's approval of the lessee's request for suspension authorizes the payment of a lesser amount during the period of approved suspension. If under the provision of this section, the Director grants a lessee's request for a suspension of production or other operations for a lease which includes provisions for a time period which the lessee may specify during which production from the leasehold would be royalty free or subject to a reduced royalty obligation pursuant to 30 CFR 581.28(b), the time during which production from a leasehold may be royalty free or subject to a reduced royalty obligation shall not be extended unless the Director's approval of the suspension specifies otherwise.
(3) If the lease anniversary date falls within a period of suspension for which no rental or minimum royalty payments are required under paragraph (a) of this section, the prorated rentals or minimum royalties are due and payable as of the date the suspension period terminates. These amounts shall be computed and notice thereof given the lessee. The lessee shall pay the amount due within 30 days after receipt of such notice. The anniversary date of a lease shall not change by reason of any period of lease suspension or rental or royalty relief resulting therefrom.
[76 FR 64462, Oct. 18, 2011, as amended at 81 FR 36153, June 6, 2016]