30 CFR § 550.1167
What information must I submit with forms and for approvals?
July 29, 2020
You must submit the supporting information listed in the following table with the form identified in column 1 and for the approval required under this subpart identified in column 2:
Open Table
SRI BOEM-0127 (2 copies) |
Reservoir reclassification | |
---|---|---|
(a) Maps: | ||
(1) Base map with surface, bottomhole, and completion locations with respect to the unit or lease line and the orientation of representative seismic lines or cross-sections | ||
(2) Structure maps with penetration point and subsea depth for each well penetrating the reservoirs, highlighting subject wells; reservoir boundaries; and original and current fluid levels | √ | √ |
(3) Net sand isopach with total net sand penetrated for each well, identified at the penetration point | * | |
(4) Net hydrocarbon isopach with net feet of pay for each well, identified at the penetration point | * | |
(b) Seismic data: | ||
(1) Representative seismic lines, including strike and dip lines that confirm the structure; indicate polarity | ||
(2) Amplitude extraction of seismic horizon, if applicable | √ | |
(c) Logs: | ||
(1) Well log sections with tops and bottoms of the reservoir(s) and proposed or existing perforations | √ | √ |
(2) Structural cross-sections showing the subject well and nearby wells | √ | |
(d) Engineering data: | ||
(1) Estimated recoverable reserves for each well completion in the reservoir; total recoverable reserves for each reservoir; method of calculation; reservoir parameters used in volumetric and decline curve analysis | √ | |
(2) Well schematics showing current and proposed conditions | ||
(3) The drive mechanism of each reservoir | √ | √ |
(4) Pressure data, by date, and whether they are estimated or measured | √ | |
(5) Production data and decline curve analysis indicative of the reservoir performance | √ | |
(6) Reservoir simulation with the reservoir parameters used, history matches, and prediction runs (include proposed development scenario) | * | |
(e) General information: | ||
(1) Detailed economic analysis | ||
(2) Reservoir name and whether or not it is competitive as defined under §250.105 | √ | √ |
(3) Operator name, lessee name(s), block, lease number, royalty rate, and unit number (if applicable) of all relevant leases | ||
(4) Geologic overview of project | √ | |
(5) Explanation of why the proposed completion scenario will maximize ultimate recovery | ||
(6) List of all wells in subject reservoirs that have ever produced or been used for injection | √ |
√Required.
*Additional items the Regional Supervisor may request.
Note: All maps must be at a standard scale and show lease and unit lines. The Regional Supervisor may waive submittal of some of the required data on a case-by-case basis.
(f) Depending on the type of approval requested, you must submit the appropriate payment of the service fee(s) listed in §550.125, according to the instructions in §550.126.