(a) An ROW grant:
(1) Includes the full length of the corridor on which a cable, pipeline, or associated facility is located;
(2) Is 200 feet (61 meters) in width, centered on the cable or pipeline, unless safety and environmental factors during construction and maintenance of the associated cable or pipeline require a greater width; and
(3) For the associated facility, is limited to the area reasonably necessary for a power or pumping station or other accessory facility.
(b) An RUE grant includes the site on which a facility or other structure is located and the areal extent of anchors, chains, and other equipment associated with a facility or other structure. The specific boundaries of an RUE will be determined by BOEM on a case-by-case basis and set forth in each RUE grant.