30 CFR § 585.600
What plans and information must I submit to BOEM before I conduct activities on my lease or grant?
July 29, 2020
You must submit a SAP, COP, or GAP and receive BOEM approval as set forth in the following table:
Open Table
Before you: | you must: |
---|---|
(a) conduct any site assessment activities on your commercial lease, | submit and obtain approval for your SAP according to §§585.605 through 585.613. |
(b) conduct any activities pertaining to construction of facilities for commercial operations on your commercial lease, | submit and obtain approval for your COP, according to §§585.620 through 585.629. |
(c) conduct any activities on your limited lease, ROW grant, or RUE grant in any OCS area, | submit and obtain approval for your GAP according to §§585.640 through 585.648. |