You must notify BOEM in writing of the following events, within the time periods provided:

(a) No later than 30 days after commencing activities associated with the placement of facilities on the lease area under a Fabrication and Installation Report.

(b) No later than 30 days after completion of construction and installation activities under a Fabrication and Installation Report.

(c) At least 7 days before commencing commercial operations.