(a) The CVA or project engineer must prepare and submit to you and BOEM all reports required by this subpart. The CVA or project engineer must also submit interim reports to you and BOEM, as requested by the BOEM.

(b) For each report required by this subpart, the CVA or project engineer must submit one electronic copy and one paper copy of each final report to BOEM. In each report, the CVA or project engineer must:

(1) Give details of how, by whom, and when the CVA or project engineer activities were conducted;

(2) Describe the CVA's or project engineer's activities during the verification process;

(3) Summarize the CVA's or project engineer's findings; and

(4) Provide any additional comments that the CVA or project engineer deems necessary.