(a) The decommissioning notice is distinct from your decommissioning application and may only be submitted following approval of your decommissioning application, as described in §§585.905 through 585.907. You must submit a decommissioning notice at least 60 days before you plan to begin decommissioning activities.

(b) Your decommissioning notice must include:

(1) A description of any changes to the approved removal methods and procedures in your approved decommissioning application, including changes to the types of vessels and equipment you will use; and

(2) An updated decommissioning schedule.

(c) We will review your decommissioning notice and may require you to resubmit a decommissioning application if BOEM determines that your decommissioning activities would:

(1) Result in a significant change in the impacts previously identified and evaluated;

(2) Require any additional Federal permits; or

(3) Propose activities not previously identified and evaluated.