30 CFR § 585.910
What must I do when I remove my facility?
July 29, 2020
(a) You must remove all facilities to a depth of 15 feet below the mudline, unless otherwise authorized by BOEM.
(b) Within 60 days after you remove a facility, you must verify to BOEM that you have cleared the site.