40 CFR § 258.26
Run-on/run-off control systems
June 9, 2020
(a) Owners or operators of all MSWLF units must design, construct, and maintain:
(1) A run-on control system to prevent flow onto the active portion of the landfill during the peak discharge from a 25-year storm;
(2) A run-off control system from the active portion of the landfill to collect and control at least the water volume resulting from a 24-hour, 25-year storm.
(b) Run-off from the active portion of the landfill unit must be handled in accordance with §258.27(a) of this part.
[56 FR 51016, Oct. 9, 1991; 57 FR 28627, June 26, 1992]