(a) Prohibited contracts. The recipient's procurement system must not allow cost-plus-percentage-of-cost (e.g., a multiplier which includes profit) or percentage-of-construction-cost types of contracts.
(b) Removal. Under a removal Cooperative Agreement, the recipient must award a fixed-price contract (lump sum, unit price, or a combination of the two) when procuring contractor support, regardless of the procurement method selected, unless the recipient obtains the award official's prior written approval.
(c) Time and material contracts. The recipient may use time and material contracts only if no other type of contract is suitable, and if the contract includes a ceiling price that the contractor exceeds at its own risk.