(a) Purpose and scope. This section sets forth the applicable State Implementation Plan (SIP) for New York under section 110 of the Clean Air Act, as amended, 42 U.S.C. 7401 et seq., and 40 CFR part 51 to meet National Ambient Air Quality Standards.

(b) Incorporation by reference.

(1) Material listed in paragraphs (c) and (d) of this section with an EPA approval date prior to August 1, 2015, was approved for incorporation by reference by the Director of the Federal Register in accordance with 5 U.S.C. 552(a) and 1 CFR part 51. Material is incorporated as it exists on the date of the approval, and notification of any change in the material will be published in the Federal Register. Entries in paragraphs (c) and (d) of this section with an EPA approval date after August 1, 2015, will be incorporated by reference in the next update to the SIP compilation.

(2) EPA Region 2 certifies that the rules/regulations provided by the EPA in the SIP compilation at the addresses in paragraph (b)(3) of this section are an exact duplicate of the officially promulgated State rules/regulations, which have been approved as part of the SIP as of August 1, 2015.

(3) Copies of the materials incorporated by reference may be inspected at the Environmental Protection Agency, Region 2, Air Programs Branch, 290 Broadway, New York, New York 10007; and the National Archives and Records Administration (NARA). For information on the availability of this material at NARA, call (202) 741-6030, or go to: www.archives.gov/federal-register/cfr/ibr-locations.html.

(c) EPA approved regulations.

EPA-Approved New York State Regulations and Laws

Open Table Open Table
State citation Title/subject State effective date EPA approval date Comments
Title 6, Part 200, Subpart 200.1 General Provisions, Definitions 5/19/2013 8/8/2019 The word odor is removed from the Subpart 200.1(d) definition of “air contaminant or air pollutant.”
Redesignation of non-attainment areas to attainment areas (200.1(av)) does not relieve a source from compliance with previously applicable requirements as per letter of Nov. 13, 1981 from H. Hovey, NYSDEC.
Changes in definitions are acceptable to EPA unless a previously approved definition is necessary for implementation of an existing SIP regulation.
EPA is including the definition of “federally enforceable” with the understanding that (1) the definition applies to provisions of a Title V permit that are correctly identified as federally enforceable, and (2) a source accepts operating limits and conditions to lower its potential to emit to become a minor source, not to “avoid” applicable requirements.
  EPA is approving incorporation by reference of those documents that are not already federally enforceable.
  EPA approval finalized at 84 FR 38878.
Title 6, Part 200, Subpart 200.6 General Provisions, Acceptable ambient air quality 2/25/2000 4/22/2008   EPA approval finalized at 73 FR 21548.
Title 6, Part 200, Subpart 200.7 General Provisions, Maintenance of equipment 2/25/2000 4/22/2008   EPA approval finalized at 73 FR 21548.
Title 6, Part 200, Subpart 200.9 General Provisions, Referenced Material 1/2/2019 8/8/2019   EPA is approving reference documents that are not Federally enforceable.
  EPA approval finalized at 84 FR 38878.
Title 6, Part 201 Permits and Registrations 4/4/1993 10/3/2005   This action removes subpart 201.5(e) from the State's Federally approved SIP.
  EPA approval finalized at 70 FR 57511.
Title 6, Part 201, Subpart 201-2.1(b)(21) Permits and Registrations, Definitions 10/15/2011 12/27/2016 EPA is including the definition of “Major stationary source or major source or major facility” with the understanding that the definition applies only to provisions of Part 231.
Revisions are approved except for changes to the definitions in 201-2.1(b)(21)(i) and 201-2.1(b)(21)(v) withdrawn by NYSDEC as per July 28, 2016 letter to EPA Region 2.
EPA approval finalized at 81 FR 95049
Title 6, Part 201, Subpart 201-7.1 Permits and Registrations, Federally Enforceable Emission Caps 7/7/1996 10/3/2005   EPA approval finalized at 70 FR 57511.
Title 6, Part 201, Subpart 201-7.2 Permits and Registrations, Emission Capping Using Synthetic Minor Permits 7/7/1996 10/3/2005   EPA approval finalized at 70 FR 57511.
Title 6, Part 202 Emissions Testing, Sampling and Analytical Determinations 3/24/1979 11/12/1981   EPA approval finalized at 46 FR 55690.
Title 6, Part 202, Subpart 202-2 Emission Statements 5/29/2005 10/31/2007   Section 202-2.3(c)(9) requires facilities to report individual HAPs that may not be classified as criteria pollutants or precursors to assist the State in air quality planning needs. EPA will not take SIP-related enforcement action on these pollutants.
  EPA approval finalized at 72 FR 61530.
Title 6, Part 204 NOX Budget Trading Program 2/25/2000 5/22/2001   Incorporates NOX SIP Call and NOX Budget Trading Program for 2003 and thereafter.
  EPA approval finalized at 66 FR 28063.
Title 6, Part 205 Architectural and Industrial Maintenance (AIM) Coatings 1/1/2011 3/8/2012   EPA approval finalized at 77 FR 13974.
Title 6, Part 207 Control Measures for an Air Pollution Episode 2/22/1979 11/12/1981   EPA approval finalized at 46 FR 55690.
Title 6, Part 211 General Prohibitions 1/1/2011 3/8/2012   Section 211.1 (previously numbered 211.2) is not part of the approved plan. (see 11/27/1998, 63 FR 65559).
  EPA approval finalized at 77 FR 13974.
Title 6, Part 212 General Process Emission Sources 9/30/2010 7/12/2013   SIP revisions submitted in accordance with §212.10(c)(3) and 212.12(c) are effective only if approved by EPA.
  EPA approval finalized at 78 FR 41846.
Title 6, Part 213 Contaminant Emissions from Ferrous Jobbing Foundries 5/1/1972 9/22/1972   EPA approval finalized at 37 FR 19814.
Title 6, Part 214 By-Product Coke Oven Batteries 9/22/1994 7/20/2006   EPA approval finalized at 71 FR 41163.
Title 6, Part 215 Open Fires 6/16/1972 9/22/1972   EPA approval finalized at 37 FR 19814.
Title 6, Part 216 Iron and/or Steel Processes 9/22/1994 7/20/2006   EPA approval finalized at 71 FR 41163.
Title 6, Part 217, Subpart 217-1 Motor Vehicle Emissions, Motor Vehicle Enhanced Inspection and Maintenance Program Requirements Until December 31, 2010 12/5/2010 2/28/2012   EPA approval finalized at 77 FR 11742.
Title 6, Part 217, Subpart 217-4 Motor Vehicle Emissions, Inspection and Maintenance Program Audits Until December 31, 2010 12/5/2010 2/28/2012   EPA approval finalized at 77 FR 11742.
Title 6, Part 217, Subpart 217-6 Motor Vehicle Emissions, Motor Vehicle Enhanced Inspection and Maintenance Program Requirements Beginning January 1, 2011 12/5/2010 2/28/2012   EPA approval finalized at 77 FR 11742.
Title 6, Part 218, Subpart 218-1 Emission Standards for Motor Vehicles and Motor Vehicle Engines, Applicability and Definitions 12/28/2000 1/31/2005   EPA's approval of part 218 only applies to light-duty vehicles.
  EPA approval finalized at 70 FR 4773.
Title 6, Part 218, Subpart 218-2 Emission Standards for Motor Vehicles and Motor Vehicle Engines, Certification and Prohibitions 12/28/2000 1/31/2005   EPA's approval of part 218 only applies to light-duty vehicles.
  EPA approval finalized at 70 FR 4773.
Title 6, Part 218, Subpart 218-3 Emission Standards for Motor Vehicles and Motor Vehicle Engines, Fleet Average 12/28/2000 1/31/2005   EPA's approval of part 218 only applies to light-duty vehicles.
  EPA approval finalized at 70 FR 4773.
Title 6, Part 218, Subpart 218-4 Emission Standards for Motor Vehicles and Motor Vehicle Engines, Zero Emissions Vehicle Sales Mandate 5/28/1992 1/6/1995   EPA's approval of part 218 only applies to light-duty vehicles.
  EPA approval finalized at 60 FR 2025.
Title 6, Part 218, Subpart 218-5 Emission Standards for Motor Vehicles and Motor Vehicle Engines, Testing 12/28/2000 1/31/2005   EPA's approval of part 218 only applies to light-duty vehicles.
  EPA approval finalized at 70 FR 4773.
Title 6, Part 218, Subpart 218-6 Emission Standards for Motor Vehicles and Motor Surveillance 12/28/2000 1/31/2005   EPA's approval of part 218 only applies to light-duty vehicles.
  EPA approval finalized at 70 FR 4773.
Title 6, Part 218, Subpart 218-7 Emission Standards for Motor Vehicles and Motor Vehicle Engines, Aftermarket Parts 12/28/2000 1/31/2005   EPA's approval of part 218 only applies to light-duty vehicles.
  EPA approval finalized at 70 FR 4773.
Title 6, Part 218, Subpart 218-8 Emission Standards for Motor Vehicles and Motor Vehicle Engines, Severability 12/28/2000 1/31/2005   EPA's approval of part 218 only applies to light-duty vehicles.
  EPA approval finalized at 70 FR 4773.
Title 6, Part 219 Incinerators 5/1/1972 9/22/1972   EPA approval finalized at 37 FR 19814.
Title 6, Part 220 Portland Cement Plants and Glass Plants 7/11/2010 7/12/2013   SIP revisions submitted in accordance with §220-1.6(b)(4) and 220-2.3(a)(4) are effective only if approved by EPA.
  EPA approval finalized at 78 FR 41846.
Title 6, Part 222 Incinerators—New York City, Nassau and Westchester Counties 6/17/1972 9/22/1972   EPA approval finalized at 37 FR 19814.
Title 6, Part 223 Petroleum Refineries 8/9/1984 7/19/1985   EPA approval finalized at 50 FR 29382.
Title 6, Part 224 Sulfuric and Nitric Acid Plants 5/10/1984 7/19/1985   Variances adopted by the State pursuant to Part 224.6(b) become applicable only if approved by EPA as SIP revisions.
  EPA approval finalized at 50 FR 29382.
Title 6, Part 225, Subpart 225-1 Fuel Composition and Use-Sulfur Limitations 4/5/2013 8/23/2018   Exceptions or Variances adopted by the State pursuant to §§225.1.3 and 1.4(b) become applicable only if approved by EPA as SIP revisions (40 CFR 52.1675(e)).
  EPA approval finalized at 83 FR 42589.
Title 6, Part 225, Subpart 225-2 Fuel Composition and Use-Waste Fuel 7/28/1983 8/2/1984   EPA approval finalized at 49 FR 30936.
Title 6, Part 225, Subpart 225-3 Fuel Composition and Use-Gasoline 11/4/2001 9/8/2005   The Variance adopted by the State pursuant to section 225-3.5 becomes applicable only if approved by EPA as a SIP revision.
  EPA approval finalized at 70 FR 53304.
Title 6, Part 226 Solvent Metal Cleaning Processes 5/7/2003 1/23/2004   EPA approval finalized at 69 FR 3237.
Title 6, Part 227, Subpart 227.2(b)(1) Stationary Combustion Installations 5/1/1972 9/22/1972   1972 version.
  EPA approval finalized at 37 FR 19814.
Title 6, Part 227, Subpart 227-1 Stationary Combustion Installations 2/25/2000 5/22/2001   Existing Part 227 is renumbered Subpart 227-1.
  Renumbered sections 227-1.2(a)(2), 227-1.4(a), and 227-1.4(d) continue to be disapproved according to 40 CFR 52.1678(d) and 52.1680(a). (New York repealed existing Part 227.5.).
  EPA approval finalized at 66 FR 28063.
Title 6, Part 227, Subpart 227-2 Stationary Combustion Installations, Reasonably Available Control Technology (RACT) For Major Facilities of Oxides of Nitrogen (NOX) 7/8/2010 7/12/2013   SIP revisions submitted in accordance with §227-2.3(c) are effective only if approved by EPA.
  EPA approval finalized at 78 FR 41846.
Title 6, Part 227, Subpart 227-3 Stationary Combustion Installations, Pre-2003 Nitrogen Oxides Emissions Budget and Allowance Program 3/5/1999 5/22/2001   Approval of NOX Budget Trading Program for 1999, 2000, 2001 and 2002. NOX caps in the State during 2003 and thereafter established in Part 204.
  EPA approval finalized at 66 FR 28063.
Title 6, Part 228 Surface Coating Processes, Commercial and Industrial Adhesives, Sealants and Primers 6/5/2013 3/4/2014   EPA approval finalized at 79 FR 12082.
Title 6, Part 229 Petroleum and Volatile Organic Liquid Storage and Transfer 4/4/1993 12/23/1997   SIP revisions submitted in accordance with Section 229.3(g)(1) are effective only if approved by EPA.
  EPA approval finalized at 62 FR 67006.
Title 6, Part 230 Gasoline Dispensing Sites and Transport Vehicles 9/22/1994 4/30/1998   EPA approval finalized at 63 FR 23668.
Title 6, Part 231 New Source Review for New and Modified Facilities 10/15/2011 12/27/2016 Full approval except for certain revisions to 231-5.5(b)(3), 231-6.6(b)(3), 231-10.1(d), 231-12.4(a)(1), 231-12.7, and 231-13.5 Table 5 withdrawn by NYSDEC as per July 28, 2016 NYSDEC letter to EPA Region 2.
The PM2.5 Significant Monitoring Concentration (SMC) is approved as 0 µg/m3 in 231-12.4(a)(1).
EPA approval finalized at 81 FR 95049
Title 6, Part 232 Dry Cleaning 8/11/1983 6/17/1985   EPA has not determined that §232.3(a) provides for reasonably available control technology.
  EPA approval finalized at 50 FR 25079.
Title 6, Part 233 Pharmaceutical and Cosmetic Manufacturing Processes 4/4/1993 12/23/1997   SIP revisions submitted in accordance with Section 223.3(h)(1) are effective only if approved by EPA.
  EPA approval finalized at 62 FR 67006.
Title 6, Part 234 Graphic Arts 7/8/2010 3/8/2012   SIP revisions submitted in accordance with §234.3(f) are effective only if approved by EPA.
  EPA approval finalized at 77 FR 13974.
Title 6, Part 235 Consumer Products 10/15/2009 5/28/2010   EPA approval finalized at 75 FR 29897.
Title 6, Part 236 Synthetic Organic Chemical Manufacturing Facility Component Leaks 1/12/1992 7/27/1993   Variances adopted by the State pursuant to Part 236.6(e)(3) become applicable only if approved by EPA as a SIP revision.
  EPA approval finalized at 58 FR 40059.
Title 6, Part 239 Portable Fuel Container Spillage Control 7/30/2009 5/28/2010   The specific application of provisions associated with alternate test methods, variances and innovative products, must be submitted to EPA as SIP revisions.
  EPA approval finalized at 75 FR 29897.
Title 6, Part 240, Subpart 240-1 Transportation Conformity, Transportation Conformity General Provisions 9/13/2013 7/29/2014   EPA approval finalized at 79 FR 43945.
Title 6, Part 240, Subpart 240-2 Transportation Conformity, Consultation 9/13/2013 7/29/2014   EPA approval finalized at 79 FR 43945.
Title 6, Part 240, Subpart 240-3 Transportation Conformity, Regional Transportation-Related Emissions and Enforceability 9/13/2013 7/29/2014   EPA approval finalized at 79 FR 43945.
Title 6, Part 241 Asphalt Pavement and Asphalt Based Surface Coating 1/1/2011 3/8/2012   EPA approval finalized at 77 FR 13974.
Title 6, Part 243 CSAPR NOX Ozone Season Group 2 Trading Program 1/2/2019 8/8/2019   EPA approval finalized at 84 FR 38878.
Title 6, Part 244 CSAPR NOX Annual Trading Program 1/2/2019 8/8/2019   EPA approval finalized at 84 FR 38878.
Title 6, Part 245 CSAPR SO2 Group 1 Trading Program 1/2/2019 8/8/2019   EPA approval finalized at 84 FR 38878.
Title 6, Part 249 Best Available Retrofit Technology (BART) 5/6/2010 8/28/2012   EPA approval finalized at 77 FR 51915.
Title 15, Part 79, Subparts 79.1-79.15, 79.17, 79.20, 79.21, 79.24, 79.25 Motor Vehicle Inspection Regulations 12/29/2010 2/28/2012   EPA approval finalized at 77 FR 11742.
Title 19, Part 937 Access To Publicly Available Records 8/27/2012 6/20/2013   Only subpart 937.1(a) is approved into the SIP and is for the limited purpose of satisfying Clean Air Act Section 128(a)(2).
  EPA approval finalized at 78 FR 37124.
Section 19-0325 Environmental Conservation Law, Sulfur reduction requirements 7/15/2010 8/28/2012   EPA approval finalized at 77 FR 51915.
Section 73-a Public Officers Law, Financial disclosure 8/15/2011 6/20/2013   Only subsections 73-a(2)(a)(i) and (ii) are approved into the SIP and are for the limited purpose of satisfying Clean Air Act Section 128(a)(2).
  EPA approval finalized at 78 FR 37124.

(d) EPA approved State source-specific requirements.

EPA-Approved New York Source-Specific Provisions

Open Table Open Table
Name of source Identifier No. State effective date EPA approval date Comments
Dunlop Tire and Rubber Corporation Consent Order 81-36, 9-0420 8/19/1981 1/26/1984   Part 212 VOC RACT Compliance Plan.
  Green tire spraying, bead dipping, and under tread and tread end cementing processes.
  EPA approval finalized at 49 FR 3436.
Dunlop Tire and Rubber Corporation Consent Order 81-36, 9-0420, Amendment Letter 1 1/29/1982 1/26/1984   Part 212 VOC RACT Compliance Plan.
  Green tire spraying, bead dipping, and under tread and tread end cementing processes.
  EPA approval finalized at 49 FR 3436.
Dunlop Tire and Rubber Corporation Consent Order 81-36, 9-0420, Amendment Letter 2 3/3/1982 1/26/1984   Part 212 VOC RACT Compliance Plan.
  Green tire spraying, bead dipping, and under tread and tread end cementing processes.
  EPA approval finalized at 49 FR 3436.
Morton International Inc. A563203003500027C 9/1/1995 9/23/1997   Part 227-2, NOX RACT determination.
  Emission point 00027.
  EPA approval finalized at 62 FR 49617.
Morton International Inc. A563203003500027C, Special Conditions 8/23/1995 9/23/1997   Part 227-2, NOX RACT determination.
  Emission point 00027.
  EPA approval finalized at 62 FR 49617.
University of Rochester 8-2614-00548/00006-0 4/25/1996 9/23/1997   Part 227-2, NOX RACT determination.
  Emission points 00003 and 0005.
  EPA approval finalized at 62 FR 49617.
University of Rochester 8-2614-00548/00006-0, Special Conditions 3/19/1996 9/23/1997   Part 227-2, NOX RACT determination.
  Emission points 00003 and 0005.
  EPA approval finalized at 62 FR 49617.
Algonquin Gas Transmission Company 3-3928-1/9-0 9/23/1991 9/23/1997   Part 227-2, NOX RACT determination.
  Emission Points R0100, R0200, R0300, and R0400.
  Permit and Special Conditions.
  EPA approval finalized at 62 FR 49617.
Algonquin Gas Transmission Company 3-3928, Special Conditions 3/18/1996 9/23/1997   Part 227-2, NOX RACT determination.
  Emission Points R0100, R0200, R0300.
  EPA approval finalized at 62 FR 49617.
Algonquin Gas Transmission Company 3-3928-00001/00013 3/29/1996 9/23/1997   Part 227-2, NOX RACT determination.
  Emission Point R0400.
  EPA approval finalized at 62 FR 49617.
Algonquin Gas Transmission Company 3-39228-00001/00010,11,12,13 8/8/1996 9/23/1997   Permit Correction.
  Part 227-2, NOX RACT determination.
  Emission Points R0100, R0200, R0300, and R0400.
  EPA approval finalized at 62 FR 49617.
Tenneco Gas Corporation's (also known as Tenneco Gas Pipeline Company and Tennessee Gas Pipeline Company) 144000 8/22/1995 7/21/2003   Part 227-2, NOX RACT determination.
  Compressor Station 229.
  Emission Points 0001A through 0006A.
  EPA approval finalized at 68 FR 42981.
Tenneco Gas Corporation's (also known as Tenneco Gas Pipeline Company and Tennessee Gas Pipeline Company) 215600, Special Conditions 2/24/1997 7/21/2003   Part 227-2, NOX RACT determination.
  Compressor Station 245.
  Emission Points 00001 through 00006.
  EPA approval finalized at 68 FR 42981.
Tenneco Gas Corporation's (also known as Tenneco Gas Pipeline Company and Tennessee Gas Pipeline Company) 102600 10/4/1995 7/21/2003   Part 227-2, NOX RACT determination.
  Compressor Station 254.
  Emission Points 00001 through 00006.
  EPA approval finalized at 68 FR 42981.
Tenneco Gas Corporation's (also known as Tenneco Gas Pipeline Company and Tennessee Gas Pipeline Company) 102600,Special Conditions 9/15/1995 7/21/2003   Part 227-2, NOX RACT determination.
  Compressor Station 254.
  Emission Points 00001 through 00006.
  EPA approval finalized at 68 FR 42981.
General Chemical Corporation 7-3132-00009/00012 12/16/1997 7/1/2004   Part 212, NOX RACT determination. 6/23/05 letter informing NYSDEC that the approval will automatically convert to a disapproval.
  Emission Points 0SN1A and 0SN1B.
  EPA approval finalized at 69 FR 39858.
ALCOA Massena Operations (West Plant) 6-4058-00003 3/20/2012 8/28/2012   Part 249 BART.
  Emission Points Potline S-00001, Baking furnace S-00002, Package Boilers B-00001.
  EPA approval finalized at 77 FR 51915.
Arthur Kill Generating Station, NRG 2-6403-00014 3/20/2012 8/28/2012   Part 249 BART.
  Boiler 30.
  EPA approval finalized at 77 FR 51915.
Bowline Generating Station, GenOn 3-3922-00003 6/28/2012 8/28/2012   Part 249 BART.
  Boilers 1 and 2.
  EPA approval finalized at 77 FR 51915.
Con Edison 59th Street Station 2-6202-00032 3/20/2012 8/28/2012   Part 249 BART.
  Steam Boilers 114 and 115.
  EPA approval finalized at 77 FR 51915.
EF Barrett Power Station, NG 1-2820-00553 3/27/2012 8/28/2012   Part 249 BART.
  Boiler 2.
  EPA approval finalized at 77 FR 51915.
International Paper Ticonderoga Mill 5-1548-00008 3/19/2012 8/28/2012   Part 249 BART.
  Power Boiler and Recovery Furnace.
  EPA approval finalized at 77 FR 51915.
Kodak Operations at Eastman Business Park, Kodak 8-2614-00205 5/25/2012 8/28/2012   Part 249 BART.
  Boilers 41, 42 and 43.
  EPA approval finalized at 77 FR 51915.
Lafarge Building Materials 4-0124-00001 7/19/2011 8/28/2012   Condition 12-14.
  Kilns 1 and 2.
  EPA approval finalized at 77 FR 51915.
Lehigh Northeast Cement, Lehigh Cement 5-5205-00013 7/5/2012 8/28/2012   Part 220 and Part 249 BART.
  Kiln and Clinker cooler.
  EPA approval finalized at 77 FR 51915.
Northport Power Station, NG 1-4726-00130 3/27/2012 8/28/2012   Part 249 BART.
  Boilers 1, 2, 3, and 4.
  EPA approval finalized at 77 FR 51915.
Oswego Harbor Power, NRG 7-3512-00030 5/16/2012 8/28/2012   Part 249 BART.
  Boilers 5 and 6.
  EPA approval finalized at 77 FR 51915.
Owens-Corning Insulating Systems Feura Bush, Owens Corning 4-0122-00004 5/18/2012 8/28/2012   Part 249 BART.
  EU2, EU3, EU12, EU13, and EU14.
  EPA approval finalized at 77 FR 51915.
Ravenswood Generating Station, TC 2-6304-00024 4/6/2012 8/28/2012   Part 249 BART.
  Boilers 10, 20, 30.
  EPA approval finalized at 77 FR 51915.
Ravenswood Steam Plant, Con Edison 2-6304-01378 3/20/2012 8/28/2012,   Part 249 BART.
  Boiler 2.
  EPA approval finalized at 77 FR 51915.
Roseton Generating Station NYSDEC Facility No. 33346000075 12/5/2016 2/16/2018 Best Available Retrofit Technology (BART) emission limits for SO2 pursuant to 6 NYCRR part 249 for Units 1 and 2.
Samuel A Carlson Generating Station, James town Board of Public Utilities 9-0608-00053 2/8/2012 8/28/2012   Part 249 BART.
  Boiler 12.
  EPA approval finalized at 77 FR 51915.
Syracuse Energy Corporation [GDF Suez] 7-3132-00052 5/24/2012 8/28/2012   Part 249 BART.
  Boiler 1.
  EPA approval finalized at 77 FR 51915.
Danskammer Energy LLC, Danskammer Generating Station NYSDEC Facility No. 33346000011 2/25/2015 12/4/2017 Best Available Retrofit Technology (BART) emission limits for NOX, SO2, and PM pursuant to 6 NYCRR part 249 for Unit 4 and the requirement to combust only natural gas.

(e) EPA approved nonregulatory and quasi-regulatory provisions.

EPA-Approved New York Nonregulatory And Quasi-Regulatory Provisions

Open Table Open Table
Action/SIP element Applicable geographic or nonattainment area New York submittal date EPA
approval date
Explanation
SIP revision for carbon monoxide concerning the oxyfuel program New York-Northern New Jersey-Long Island carbon monoxide nonattainment area 8/30/1999 4/19/2000, 65 FR 20909
Stage II gasoline vapor recovery comparability plan Upstate portions of New York State 4/18/2000 9/29/2000, 65 FR 58364
The 1990 base year emission inventory (Volatile organic compounds (VOC), Nitrogen oxides (NOX) and Carbon monoxide (CO)) Areas designated nonattainment for ozone since 1991 in New York State 2/2/1999 5/10/2001, 66 FR 23851
1996 and 1999 ozone projection year emission inventories New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 2/2/1999 5/10/2001, 66 FR 23851
Photochemical assessment monitoring stations network New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 2/2/1999 5/10/2001, 66 FR 23851
Enforceable commitments for ozone New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 2/2/1999 5/10/2001, 66 FR 23851
15 Percent Rate of Progress Plan and the 9 Percent Reasonable Further Progress Plan for ozone New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 2/2/1999 5/10/2001, 66 FR 23851
2002, 2005 and 2007 ozone projection year emission inventories New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 11/27/1998 2/4/2002, 67 FR 5194
Reasonable Further Progress Plans for milestone years 2002, 2005 and 2007 for ozone New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 11/27/1998 2/4/2002, 67 FR 5194
Contingency measures for ozone New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 11/27/1998 2/4/2002, 67 FR 5194
Reasonably Available Control Measure Analysis for ozone New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 10/1/2001 2/4/2002, 67 FR 5194
Attainment demonstration for ozone New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 11/27/1998, supplemented on 4/15/1999, and 4/18/2000 2/4/2002, 67 FR 5194
Enforceable commitments for future actions associated with attainment of the 1-hour ozone national ambient air quality standard New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 4/18/2000 2/4/2002, 67 FR 5194
SIP revision to the carbon monoxide maintenance plan Onondaga County 6/22/2004 9/8/2005, 70 FR 53304
1990 and 2007 conformity emission budgets for ozone New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 1/29/2003, amended on
6/29/2003 and 1/18/2005
9/13/2005, 70 FR 53944
Revised commitment to perform a mid-course review for ozone New York portion of the New York-Northern New Jersey-Long Island 1-hour ozone nonattainment area 1/29/2003 9/13/2005, 70 FR 53944
New York reasonably available control technology (RACT) analysis for ozone Statewide and to the New York portion of the New York-Northern New Jersey-Long Island, NY-NJ-CT and the Poughkeepsie 8-hour ozone moderate nonattainment areas 9/1/06, supplemented on 2/8/2008 and 9/16/2008 7/23/2010, 75 FR 43069
Reasonably available control measure (RACM) analysis for ozone New York portion of the New York-Northern New Jersey-Long Island, NY-NJ-CT 8-hour ozone moderate nonattainment area 2/8/2008 7/23/2010, 75 FR 43069
2002 base year emissions inventory;
2008 projection year emissions inventories;
2008 motor vehicle emissions budgets used for planning purposes;
2008 ozone reasonable further progress (RFP) plan; and
2008 RFP Plan contingency measures.
New York portion of the New York-Northern New Jersey-Long Island 8-hour ozone nonattainment area 2/8/2008 supplemented
on 12/28/2009 and 1/26/2011
August 18, 2011
2002 base year emissions inventory Poughkeepsie 8-hour ozone moderate nonattainment area 2/8/2008 supplemented
on 12/28/2009 and 1/26/2011
August 18, 2011
2002 base year emissions inventory State-wide 2/8/2008 supplemented
on 12/28/2009 and 1/26/2011
August 18, 2011
Implementation Plan for Regional Haze Statewide 3/15/2000 8/28/2012, 77 FR 51915 The plan is approved except for the BART determinations for Danskammer Generating Station Unit 4 and Roseton Generating Station Units 1 and 2. See 40 CFR 52.1686.
Regional Haze plan—Fuel Oil Sulfur Content Statewide 4/16/2012 8/28/2012, 77 FR 51915
Regional Haze Plan—BART Permit modifications Statewide 4/16/2012 8/28/2012, 77 FR 51915
Regional Haze Plan—BART Permit modifications Statewide 7/2/2012 8/28/2012, 77 FR 51915
1997 8-hour Ozone—Attainment Demonstration New York portion of the New York-Northern New Jersey-Long Island, NY-NJ-CT 8-hour ozone moderate nonattainment area 2/8/2008 2/11/2013, 78 FR 9596
1997 8-hour Ozone—Attainment Demonstration Poughkeepsie 8-hour ozone moderate nonattainment area 2/8/2008 2/11/2013, 78 FR 9596
Section 110(a)(2) Infrastructure Requirements for the 1997 8-hour ozone and the 1997 and 2006 PM2.5 NAAQS Statewide 12/13/2007, 10/2/2008,
3/15/2010 and supplemented on 5/23/2013
6/20/2013, 78 FR 37122 This action addresses the following CAA elements: 110(a)(2)(A), (B), (C), (D)(i)(II) prongs 3 and 4, (D)(ii), (E), (F), (G), (H), (J), (K), (L), and (M).
Maintenance plan for the 1997 and 2006 PM2.5 National Ambient Air Quality Standards. 2007 attainment year emissions inventory. 2009, 2017, and 2025 motor vehicle emissions budget New York portion of the 1997 and 2006 New York-Northern New Jersey-Long         Island, NY-NJ-CT, PM2.5 nonattainment area 6/27/2013 and supplemented on 9/18/2013 and 2/27/2014 4/18/2014, 79 FR 21857
Approval of CO maintenance plan, CO motor vehicle budgets, and 2007 CO base year emissions inventory New York portion of the New York-Northern New Jersey-Long Island (NYCMA) CO area 5/9/2013 5/30/2014, 79 FR 31045 This is the 2nd 10-year CO maintenance plan for the New York portion of the NYCMA.
Section 110(a)(2) Infrastructure Requirements for the 2010 Primary Nitrogen Dioxide NAAQS Statewide 5/8/2013, and supplemented on 5/23/2013 9/12/2014, 79 FR 54619 This action addresses the following CAA elements: 110(a)(2)(A), (B), (C), (D), (E), (F), (G), (H), (J), (K), (L), and (M).
Section 110(a)(2) Infrastructure Requirements for the 2008 Primary Pb NAAQS Statewide 10/13/2011, and supplemented on 2/24/2012 6/1/2015, 80 FR 30940 This action addresses the following CAA elements: 110(a)(2)(A), (B), (D)(i)(I) prongs 1 and 2, D(i)(II) prong 4, (E), (F), (G), (H), (K), (L), and (M).
Limited off-street parking program New York County—Central Business District 10/5/2012 6/12/2015, 80 FR 33425 Removing reference to program from SIP.
Section 110(a)(2) Infrastructure Requirements for the 2008 ozone NAAQS Statewide 4/4/2013 8/26/2016, 81 FR 58854 This action addresses the following CAA element: 110(a)(2)(D(i)(II) prong 4.
Section 110(a)(2) Infrastructure Requirements for the 2008 ozone NAAQS Statewide 4/4/2013 12/27/2016, 81 FR 95049 This action addresses the following CAA elements: 110(a)(2)(C), (D)(i)(II) prong 3, and (J).
Section 110(a)(2) Infrastructure Requirements for the 2008 Pb NAAQS Statewide 10/13/2011, and supplemented on 2/24/2012 12/27/2016, 81 FR 95049 This action addresses the following CAA elements: 110(a)(2)(C), (D)(i)(II) prong 3, and (J).
Section 110(a)(2) Infrastructure Requirements for the 2010 SO2 NAAQS Statewide 10/3/2013 12/27/2016, 81 FR 95049 This action addresses the following CAA elements: 110(a)(2)(C), (D)(i)(II) prong 3, and (J).
Regional Haze Five-Year Progress Report State-wide 6/16/2015 9/29/2017, 82 FR 45499
2008 8-hour Ozone RACT analysis Statewide and to the New York portion of the New York-Northern New Jersey-Long Island (NY-NJ-CT) and the Jamestown 8-hour ozone nonattainment areas 12/22/2014 12/12/2017   Full approval as it applies to non-CTG major sources of VOCs and to major sources of NOX.
  Conditional approval as it applies to CTG for VOC major sources.
2008 8-hour Ozone Nonattainment New Source Review Requirements Statewide and to the New York portion of the New York-Northern New Jersey-Long Island (NY-NJ-CT) and the Jamestown 8-hour ozone nonattainment areas 12/22/2014 12/12/2017   Full approval.
Section 185 fee program State-wide 1/31/2014, supplemented on 4/7/2014, 10/13/2016, and 4/3/2018 4/2/2019, 84 FR 12511 Approval of the Low Emissions Vehicle Program (LEV II) as an alternative section 185 fee program
Section 110(a)(2) Infrastructure Requirements for the 2008 Ozone NAAQS Statewide 4/4/2013 10/10/2019, 84 FR 54502 This action addresses the following CAA elements: 110(a)(2)(A), (B), (D)(ii), (E), (F), (G), (H), (K), (L) and (M).
Section 110(a)(2) Infrastructure Requirements for the 2010 SO2 NAAQS Statewide 10/3/2013 10/10/2019, 84 FR 54502 This action addresses the following CAA elements: 110(a)(2)(A), (B), (D)(i)(II) prong 4, (D)(ii), (E), (F), (G), (H), (K), (L) and (M).
Section 110(a)(2) Infrastructure Requirements for the 2012 PM2.5 NAAQS Statewide 11/30/2016 10/10/2019, 84 FR 54502 This action addresses the following CAA elements: 110(a)(2)(A), (B), (C) [enforcement measures and PSD program for major sources], (D)(i)(II) prong 3, (D)(ii), (E), (F), (G), (H), (J) [for consultation, public notification and prevention of significant deterioration] (K), (L) and (M).

[76 FR 41707, July 15, 2011, as amended at 76 FR 51266, Aug. 19, 2011; 77 FR 11743, Feb. 28, 2012; 77 FR 13977, Mar. 8, 2012; 77 FR 51926, Aug. 28, 2012; 78 FR 9597, Feb. 11, 2013; 78 FR 37124, June 20, 2013; 78 FR 41849, July 12, 2013; 79 FR 12084, Mar. 4, 2014; 79 FR 21857, Apr. 18, 2014; 79 FR 31046, May 30, 2014; 79 FR 43945, July 29, 2014; 79 FR 54619, Sept. 12, 2014; 80 FR 30940, June 1, 2015; 80 FR 33425, June 12, 2015; 81 FR 23169, Apr. 20, 2016; 81 FR 58854, Aug. 26, 2016; 81 FR 95049, Dec. 27, 2016; 82 FR 45500, Sept. 29, 2017; 82 FR 57129, Dec. 4, 2017; 82 FR 57366, Dec. 5, 2017; 82 FR 58346, Dec. 12, 2017; 83 FR 33, Jan. 2, 2018; 83 FR 6972, Feb. 16, 2018; 83 FR 42591, Aug. 23, 2018; 84 FR 12513, Apr. 2, 2019; 84 FR 22981, May 21, 2019; 84 FR 38881, Aug. 8, 2019; 84 FR 54506, Oct. 10, 2019]


Tried the LawStack mobile app?

Join thousands and try LawStack mobile for FREE today.

  • Carry the law offline, wherever you go.
  • Download CFR, USC, rules, and state law to your mobile device.