Table 1 of this section shows which parts of the General Provisions in §§63.1 through 63.15 apply to you. Table 1 of §63.2870 follows:

Table 1 to §63.2870—Applicability of 40 CFR Part 63, Subpart A, to 40 CFR, Part 63, Subpart GGGG

Open Table
General provisions citation Subject of citation Brief description of requirement Applies to subpart Explanation
§63.1 Applicability Initial applicability determination; applicability after standard established; permit requirements; extensions; notifications Yes
§63.2 Definitions Definitions for part 63 standards Yes Except as specifically provided in this subpart.
§63.3 Units and abbreviations Units and abbreviations for part 63 standards Yes
§63.4 Prohibited activities and circumvention Prohibited activities; compliance date; circumvention; severability Yes
§63.5 Construction/reconstruction Applicability; applications; approvals Yes Except for subsections of §63.5 as listed below.
§63.5(c) [Reserved]
§63.5(d)(1)(ii)(H) Application for approval Type and quantity of HAP, operating parameters No All sources emit HAP. Subpart GGGG does not require control from specific emission points.
§63.5(d)(1)(ii)(I) [Reserved]
§63.5(d)(1)(iii), (d)(2), (d)(3)(ii) Application for approval No The requirements of the application for approval for new, reconstructed and significantly modified sources are described in §63.2860(b) and (c) of subpart GGGG. General provision requirements for identification of HAP emission points or estimates of actual emissions are not required. Descriptions of control and methods, and the estimated and actual control efficiency of such do not apply. Requirements for describing control equipment and the estimated and actual control efficiency of such equipment apply only to control equipment to which the subpart GGGG requirements for quantifying.
§63.6 Applicability of General Provisions Applicability Yes Except for subsections of §63.6 as listed below.
§63.6(b)(1)-(3) Compliance dates, new and reconstructed sources No Section 63.2834 of subpart GGGG specifies the compliance dates for new and reconstructed sources.
§63.6(b)(6) [Reserved]
§63.6(c)(3)-(4) [Reserved]
§63.6(d) [Reserved]
§63.6(e)(1)(i) Operation and Maintenance Yes, before September 15, 2020. No, on or after September 15, 2020 See §63.2840(g) for general duty requirement
§63.6(e)(1)(ii) Operation and Maintenance Requirement to correct malfunctions as soon as practicable Yes, before September 15, 2020]. No, on or after September 15, 2020 See §63.2840(g) for general duty requirement.
§63.6(e)(3)(i) through (e)(3)(ii) and §63.6(e)(3)(v) through (vii) Operation and maintenance requirements Yes, before September 15, 2020 Minimize emissions to the extent practicable. On or after September 15, 2020, see §63.2840(g) for general duty requirement.
§63.6(e)(3)(iii) Operation and maintenance requirements No Minimize emissions to the extent practicable. On or after September 15, 2020, see §63.2840(g) for general duty requirement.
§63.6(e)(3)(iv) Operation and maintenance requirements No Report SSM and in accordance with §63.2861(c) and (d).
§63.6(e)(3)(viii) Operation and maintenance requirements Yes, before September 15, 2020. No, on or after September 15, 2020 Except, before September 15, 2020, report each revision to your SSM plan in accordance with §63.2861(c) rather than §63.10(d)(5) as required under §63.6(e)(3)(viii).
§63.6(e)(3)(ix) Title V permit Yes, before September 15, 2020. No, on or after September 15, 2020
§63.6(f)(1) Compliance with nonopacity emission standards except during SSM Comply with emission standards at all times except during SSM Yes, before September 15, 2020. No, on or after September 15, 2020
§63.6(f)(2)-(3) Methods for Determining Compliance Yes
§63.6(g) Use of an Alternative Standard Yes
§63.6(h) Opacity/Visible emission (VE) standards No Subpart GGGG has no opacity or VE standards.
§63.6(i) Compliance extension Procedures and criteria for responsible agency to grant compliance extension Yes.
§63.6(j) Presidential compliance exemption President may exempt source category from requirement to comply with subpart Yes.
§63.7(e)(1) Performance testing requirements Representative conditions for performance test Yes, before September 15, 2020. No, on or after September 15, 2020 See §63.2853(a)(5)(i)(A) for performance testing requirements.
§63.7(e)(2)-(4), (f), (g), and (h) Performance testing requirements Schedule, conditions, notifications and procedures Yes Subpart GGGG requires performance testing only if the source applies additional control that destroys solvent. Section 63.2850(a)(6) requires sources to follow the performance testing guidelines of the General Provisions if a control is added.
§63.8 Monitoring requirements No Subpart GGGG does not require monitoring other than as specified therein.
§63.9 Notification requirements Applicability and state delegation Yes Except for subsections of §63.9 as listed below.
§63.9(b)(2) Notification requirements Initial notification requirements for existing sources No Section 63.2860(a) of subpart GGGG specifies the requirements of the initial notification for existing sources.
§63.9(b)(3)-(5) Notification requirements Notification requirement for certain new/reconstructed sources Yes Except the information requirements differ as described in §63.2860(b) of subpart GGGG.
§63.9(e) Notification of performance test Notify responsible agency 60 days ahead Yes Applies only if performance testing is performed.
§63.9(f) Notification of VE/opacity observations Notify responsible agency 30 days ahead No Subpart GGGG has no opacity or VE standards.
§63.9(g) Additional notifications when using a continuous monitoring system (CMS) Notification of performance evaluation; Notification using COMS data; notification that exceeded criterion for relative accuracy No Subpart GGGG has no CMS requirements.
§63.9(h) Notification of compliance status Contents No Section 63.2860(d) of subpart GGGG specifies requirements for the notification of compliance status.
§63.10 Recordkeeping/reporting Schedule for reporting, record storage Yes Except for subsections of §63.10 as listed below.
§63.10(b)(2)(i) Recordkeeping Record SSM event Yes, before September 15, 2020. No, on or after September 15, 2020 Before September 15, 2020, applicable to periods when sources must implement their SSM plan as specified in subpart GGGG. On or after September 15, 2020, meet the requirements of §63.2862(f).
§63.10(b)(2)(ii)-(iii) Recordkeeping Malfunction of air pollution equipment No Before September 15, 2020, applies only if air pollution control equipment has been added to the process and is necessary for the source to meet the emission limit. On or after September 15, 2020, meet the requirements of §63.2862(g).
§63.10(b)(2)(iv)-(v) Recordkeeping SSM recordkeeping Yes, before September 15, 2020. No, on or after September 15, 2020
§63.10(b)(2)(vi) Recordkeeping CMS recordkeeping No Subpart GGGG has no CMS requirements.
§63.10(b)(2)(viii)-(ix) Recordkeeping Conditions of performance test Yes Applies only if performance tests are performed. Subpart GGGG does not have any CMS opacity or VE observation requirements.
§63.10(b)(2)(x)-(xii) Recordkeeping CMS, performance testing, and opacity and VE observations recordkeeping No Subpart GGGG does not require CMS.
§63.10(c) Recordkeeping Additional CMS recordkeeping No Subpart GGGG does not require CMS.
§63.10(d)(2) Reporting Reporting performance test results Yes Applies only if performance testing is performed.
§63.10(d)(3) Reporting Reporting opacity or VE observations No Subpart GGGG has no opacity or VE standards.
§63.10(d)(4) Reporting Progress reports Yes Applies only if a condition of compliance extension exists.
§63.10(d)(5) Reporting SSM reporting No Section 63.2861(c) and (d) specify SSM reporting requirements.
§63.10(e) Reporting Additional CMS reports No Subpart GGGG does not require CMS.
§63.11 Control device requirements Requirements for flares Yes Applies only if your source uses a flare to control solvent emissions. Subpart GGGG does not require flares.
§63.12 State authority and delegations State authority to enforce standards Yes
§63.13 State/regional addresses Addresses where reports, notifications, and requests are sent Yes
§63.14 Incorporation by reference Test methods incorporated by reference Yes
§63.15 Availability of information and confidentiality Public and confidential information Yes

[66 FR 19011, Apr. 12, 2001, as amended at 67 FR 16321, Apr. 5, 2002; 71 FR 20463, Apr. 20, 2006; 85 FR 15632, Mar. 18, 2020]


Tried the LawStack mobile app?

Join thousands and try LawStack mobile for FREE today.

  • Carry the law offline, wherever you go.
  • Download CFR, USC, rules, and state law to your mobile device.