A complete Acid Rain permit application shall include the following elements in a format prescribed by the Administrator:
(a) Identification of the affected source for which the permit application is submitted;
(b) Identification of each Phase I unit at the source for which the permit application is submitted for Phase I or each affected unit (except for an opt-in source) at the source for which the permit application is submitted for Phase II;
(c) A complete compliance plan for each unit, in accordance with subpart D of this part;
(d) The standard requirements under §72.9; and
(e) If the Acid Rain permit application is for Phase II and the unit is a new unit, the date that the unit has commenced or will commence operation and the deadline for monitor certification.
[58 FR 3650, Jan. 11, 1993, as amended at 62 FR 55480, Oct. 24, 1997]