40 CFR Table 2
Applicability of General Provisions to Subpart PPPP of Part 63
June 9, 2020
You must comply with the applicable General Provisions requirements according to the following table
Open Table
Citation | Subject | Applicable to subpart PPPP |
Explanation |
---|---|---|---|
§63.1(a)(1)-(14) | General Applicability | Yes. | |
§63.1(b)(1)-(3) | Initial Applicability Determination | Yes | Applicability to subpart PPPP is also specified in §63.4481. |
§63.1(c)(1) | Applicability After Standard Established | Yes. | |
§63.1(c)(2)-(3) | Applicability of Permit Program for Area Sources | No | Area sources are not subject to subpart PPPP. |
§63.1(c)(4)-(5) | Extensions and Notifications | Yes. | |
§63.1(e) | Applicability of Permit Program Before Relevant Standard is Set | Yes. | |
§63.2 | Definitions | Yes | Additional definitions are specified in §63.4581. |
§63.3(a)-(c) | Units and Abbreviations | Yes. | |
§63.4(a)(1)-(5) | Prohibited Activities | Yes. | |
§63.4(b)-(c) | Circumvention/Severability | Yes. | |
§63.5(a) | Construction/Reconstruction | Yes. | |
§63.5(b)(1)-(6) | Requirements for Existing, Newly Constructed, and Reconstructed Sources | Yes. | |
§63.5(d) | Application for Approval of Construction/Reconstruction | Yes. | |
§63.5(e) | Approval of Construction/Reconstruction | Yes. | |
§63.5(f) | Approval of Construction/Reconstruction Based on Prior State Review | Yes. | |
§63.6(a) | Compliance With Standards and Maintenance Requirements—Applicability | Yes. | |
§63.6(b)(1)-(7) | Compliance Dates for New and Reconstructed Sources | Yes | Section 63.4483 specifies the compliance dates. |
§63.6(c)(1)-(5) | Compliance Dates for Existing Sources | Yes | Section 63.4483 specifies the compliance dates. |
§63.6(e)(1)-(2) | Operation and Maintenance | Yes. | |
§63.6(e)(3) | Startup, Shutdown, and Malfunction Plan | Yes | Only sources using an add-on control device to comply with the standard must complete startup, shutdown, and malfunction plans. |
§63.6(f)(1) | Compliance Except During Startup, Shutdown, and Malfunction | Yes | Applies only to sources using an add-on control device to comply with the standard. |
§63.6(f)(2)-(3) | Methods for Determining Compliance | Yes. | |
§63.6(g)(1)-(3) | Use of an Alternative Standard | Yes. | |
§63.6(h) | Compliance With Opacity/Visible Emission Standards | No | Subpart PPPP does not establish opacity standards and does not require continuous opacity monitoring systems (COMS). |
§63.6(i)(1)-(16) | Extension of Compliance | Yes. | |
§63.6(j) | Presidential Compliance Exemption | Yes. | |
§63.7(a)(1) | Performance Test Requirements—Applicability | Yes | Applies to all affected sources. Additional requirements for performance testing are specified in §§63.4564, 63.4565, and 63.4566. |
§63.7(a)(2) | Performance Test Requirements—Dates | Yes | Applies only to performance tests for capture system and control device efficiency at sources using these to comply with the standards. Section 63.4560 specifies the schedule for performance test requirements that are earlier than those specified in §63.7(a)(2). |
§63.7(a)(3) | Performance Tests Required By the Administrator | Yes. | |
§63.7(b)-(e) | Performance Test Requirements—Notification, Quality Assurance, Facilities Necessary for Safe Testing, Conditions During Test | Yes | Applies only to performance tests for capture system and add-on control device efficiency at sources using these to comply with the standards. |
§63.7(f) | Performance Test Requirements—Use Alternative Test Method | Yes | Applies to all test methods except those of used to determine capture system efficiency. |
§63.7(g)-(h) | Performance Test Requirements—Data Analysis, Recordkeeping, Reporting, Waiver of Test | Yes | Applies only to performance tests for capture system and add-on control device efficiency at sources using these to comply with the standards. |
§63.8(a)(1)-(3) | Monitoring Requirements—Applicability | Yes | Applies only to monitoring of capture system and add-on control device efficiency at sources using these to comply with the standards. Additional requirements for monitoring are specified in §63.4568. |
§63.8(a)(4) | Additional Monitoring Requirements | No | Subpart PPPP does not have monitoring requirements for flares. |
§63.8(b) | Conduct of Monitoring | Yes. | |
§63.8(c)(1)-(3) | Continuous Monitoring Systems (CMS) Operation and Maintenance | Yes | Applies only to monitoring of capture system and add-on control device efficiency at sources using these to comply with the standard. Additional requirements for CMS operations and maintenance are specified in §63.4568. |
§63.8(c)(4) | CMS | No | Section 63.4568 specifies the requirements for the operation of CMS for capture systems and add-on control devices at sources using these to comply. |
§63.8(c)(5) | COMS | No | Subpart PPPP does not have opacity or visible emission standards. |
§63.8(c)(6) | CMS Requirements | No | Section 63.4568 specifies the requirements for monitoring systems for capture systems and add-on control devices at sources using these to comply. |
§63.8(c)(7) | CMS Out-of-Control Periods | Yes. | |
§63.8(c)(8) | CMS Out-of-Control Periods and Reporting | No | Section 63.4520 requires reporting of CMS out-of-control periods. |
§63.8(d)-(e) | Quality Control Program and CMS Performance Evaluation | No | Subpart PPPP does not require the use of continuous emissions monitoring systems. |
§63.8(f)(1)-(5) | Use of an Alternative Monitoring Method | Yes. | |
§63.8(f)(6) | Alternative to Relative Accuracy Test | No | Subpart PPPP does not require the use of continuous emissions monitoring systems. |
§63.8(g)(1)-(5) | Data Reduction | No | Sections 63.4567 and 63.4568 specify monitoring data reduction. |
§63.9(a)-(d) | Notification Requirements | Yes. | |
§63.9(e) | Notification of Performance Test | Yes | Applies only to capture system and add-on control device performance tests at sources using these to comply with the standards. |
§63.9(f) | Notification of Visible Emissions/Opacity Test | No | Subpart PPPP does not have opacity or visible emission standards. |
§63.9(g)(1)-(3) | Additional Notifications When Using CMS | No | Subpart PPPP does not require the use of continuous emissions monitoring systems. |
§63.9(h) | Notification of Compliance Status | Yes | Section 63.4510 specifies the dates for submitting the notification of compliance status. |
§63.9(i) | Adjustment of Submittal Deadlines | Yes. | |
§63.9(j) | Change in Previous Information | Yes. | |
§63.10(a) | Recordkeeping/Reporting—Applicability and General Information | Yes. | |
§63.10(b)(1) | General Recordkeeping Requirements | Yes | Additional requirements are specified in §§63.4530 and 63.4531. |
§63.10(b)(2) (i)-(v) | Recordkeeping Relevant to Startup, Shutdown, and Malfunction Periods and CMS | Yes | Requirements for startup, shutdown, and malfunction records only apply to add-on control devices used to comply with the standards. |
§63.10(b)(2) (vi)-(xi) | Yes. | ||
§63.10(b)(2) (xii) | Records | Yes. | |
§63.10(b)(2) (xiii) | No | Subpart PPPP does not require the use of continuous emissions monitoring systems. | |
§63.10(b)(2) (xiv) | Yes. | ||
§63.10(b)(3) | Recordkeeping Requirements for Applicability Determinations | Yes. | |
§63.10(c)(1)-(6) | Additional Recordkeeping Requirements for Sources with CMS | Yes | |
§63.10(c)(7)-(8) | No | The same records are required in §63.4520(a)(7). | |
§63.10(c)(9)-(15) | Yes. | ||
§63.10(d)(1) | General Reporting Requirements | Yes | Additional requirements are specified in §63.4520. |
§63.10(d)(2) | Report of Performance Test Results | Yes | Additional requirements are specified in §63.4520(b). |
§63.10(d)(3) | Reporting Opacity or Visible Emissions Observations | No | Subpart PPPP does not require opacity or visible emissions observations. |
§63.10(d)(4) | Progress Reports for Sources With Compliance Extensions | Yes. | |
§63.10(d)(5) | Startup, Shutdown, and Malfunction Reports | Yes | Applies only to add-on control devices at sources using these to comply with the standards. |
§63.10(e)(1)-(2) | Additional CMS Reports | No | Subpart PPPP does not require the use of continuous emissions monitoring systems. |
§63.10(e)(3) | Excess Emissions/CMS Performance Reports | No | Section 63.4520(b) specifies the contents of periodic compliance reports. |
§63.10(e)(4) | COMS Data Reports | No | Subpart PPPP does not specify requirements for opacity or COMS. |
§63.10(f) | Recordkeeping/Reporting Waiver | Yes. | |
§63.11 | Control Device Requirements/Flares | No | Subpart PPPP does not specify use of flares for compliance. |
§63.12 | State Authority and Delegations | Yes. | |
§63.13 | Addresses | Yes. | |
§63.14 | Incorporation by Reference | Yes. | |
§63.15 | Availability of Information/Confidentiality | Yes. |