You must comply with the applicable General Provisions requirements according to the following table:

Open Table
Citation Subject Applicable to subpart KKKK Explanation
§63.1(a)(1)-(4) General Applicability Yes
§63.1(a)(6) Source Category Listing Yes
§63.1(a)(10)-(12) Timing and Overlap Clarifications Yes
§63.1(b)(1) Initial Applicability Determination Yes Applicability to subpart KKKK is also specified in §63.3481.
§63.1(b)(3) Applicability Determination Recordkeeping Yes
§63.1(c)(1) Applicability after Standard Established Yes
§63.1(c)(2) Applicability of Permit Program for Area Sources No Area sources are not subject to subpart KKKK.
§63.1(c)(5) Extensions and Notifications Yes
§63.1(e) Applicability of Permit Program before Relevant Standard is Set Yes
§63.2 Definitions Yes Additional definitions are specified in §63.3561.
§63.3 Units and Abbreviations Yes
§63.4(a)(1)-(2) Prohibited Activities Yes
§63.4(b)-(c) Circumvention/Fragmentation Yes
§63.5(a) Construction/Reconstruction Yes
§63.5(b)(1), (3), (4), (6) Requirements for Existing, Newly Constructed, and Reconstructed Sources Yes
§63.5(d)(1)(i)-(ii)(F), (d)(1)(ii)(H), (d)(1)(ii)(J), (d)(1)(iii), (d)(2)-(4) Application for Approval of Construction/Reconstruction Yes
§63.5(e) Approval of Construction/Reconstruction Yes
§63.5(f) Approval of Construction/Reconstruction Based on Prior State Review Yes
§63.6(a) Compliance with Standards and Maintenance Requirements—Applicability Yes
§63.6(b)(1)-(5), (b)(7) Compliance Dates for New and Reconstructed Sources Yes Section 63.3483 specifies the compliance dates.
§63.6(c)(1), (2), (5) Compliance Dates for Existing Sources Yes Section 63.3483 specifies the compliance dates.
§63.6(e)(1)(i)-(ii) Operation and Maintenance Yes before August 24, 2020, No on and after August 24, 2020 See §63.3500(b) for general duty requirement.
§63.6(e)(1)(iii) Operation and Maintenance Yes
§63.6(e)(3)(i), (e)(3)(iii)-(ix) SSMP Yes before August 24, 2020, No on and after August 24, 2020
§63.6(f)(1) Compliance Except during Startup, Shutdown, and Malfunction Yes before August 24, 2020, No on and after August 24, 2020
§63.6(f)(2)-(3) Methods for Determining Compliance Yes
§63.6(g) Use of an Alternative Standard Yes
§63.6(h) Compliance with Opacity/Visible Emission Standards No Subpart KKKK does not establish opacity standards and does not require continuous opacity monitoring systems (COMS).
§63.6(i)(1)-(14) Extension of Compliance Yes
§63.6(i)(16) Compliance Extensions and Administrator's Authority Yes
§63.6(j) Presidential Compliance Exemption Yes
§63.7(a)(1) Performance Test Requirements—Applicability Yes Applies to all affected sources. Additional requirements for performance testing are specified in §§63.3543, 63.3544, 63.3545, 63.3554, and 63.3555.
§63.7(a)(2) except (a)(2)(i)-(viii) Performance Test Requirements—Dates Yes Applies only to performance tests for capture system and control device efficiency at sources using these to comply with the standards. Sections 63.3540 and 63.3550 specify the schedule for performance test requirements that are earlier than those specified in §63.7(a)(2).
§63.7(a)(3) Performance Tests Required by the Administrator Yes
§63.7(b)-(d) Performance Test Requirements—Notification, Quality Assurance, Facilities Necessary for Safe Testing, Conditions During Test Yes Applies only to performance tests for capture system and add-on control device efficiency at sources using these to comply with the standards.
§63.7(e)(1) Conduct of Performance Tests Yes before August 24, 2020, No on and after August 24, 2020 See §§63.3543 and 63.3553.
§63.7(e)(2)-(4) Conduct of Performance Tests Yes
§63.7(f) Performance Test Requirements—Use of Alternative Test Method Yes Applies to all test methods except those used to determine capture system efficiency.
§63.7(g)-(h) Performance Test Requirements—Data Analysis, Recordkeeping, Reporting, Waiver of Test Yes Applies only to performance tests for capture system and add-on control device efficiency at sources using these to comply with the standards.
§63.8(a)(1)-(2) Monitoring Requirements—Applicability Yes Applies only to monitoring of capture system and add-on control device efficiency at sources using these to comply with the standards. Additional requirements for monitoring are specified in §§63.3547 and 63.3557.
§63.8(a)(4) Additional Monitoring Requirements No Subpart KKKK does not have monitoring requirements for flares.
§63.8(b) Conduct of Monitoring Yes
§63.8(c)(1) Continuous Monitoring System (CMS) Operation and Maintenance Yes before August 24, 2020, No on and after August 24, 2020 Sections 63.3547 and 63.3557 specify the requirements for the operation of CMS for capture systems and add-on control devices at sources using these to comply.
§63.8(c)(2)-(3) CMS Operation and Maintenance Yes Applies only to monitoring of capture system and add-on control device efficiency at sources using these to comply with the standards. Additional requirements for CMS operations and maintenance are specified in §§63.3547 and 63.3557.
§63.8(c)(4) CMS No Sections 63.3547 and 63.3557 specify the requirements for the operation of CMS for capture systems and add-on control devices at sources using these to comply.
§63.8(c)(5) COMS No Subpart KKKK does not have opacity or visible emission standards.
§63.8(c)(6) CMS Requirements No Sections 63.3547 and 63.3557 specify the requirements for monitoring systems for capture systems and add-on control devices at sources using these to comply.
§63.8(c)(7) CMS Out-of-Control Periods Yes
§63.8(c)(8) CMS Out-of-Control Periods Reporting No Section 63.3511 requires reporting of CMS out of control periods.
§63.8(d)-(e) Quality Control Program and CMS Performance Evaluation No
§63.8(f)(1)-(5) Use of an Alternative Monitoring Method Yes
§63.8(f)(6) Alternative to Relative Accuracy Test No Section 63.8(f)(6) provisions are not applicable because subpart KKKK does not require CEMS.
§63.8(g) Data Reduction No Sections 63.3542, 63.3547, 63.3552 and 63.3557 specify monitoring data reduction.
§63.9(a) Notification Applicability Yes
§63.9(b)(1)-(2) Initial Notifications Yes
§63.9(b)(4)(i), (b)(4)(v), (b)(5) Application for Approval of Construction or Reconstruction Yes
§63.9(c) Request for Extension of Compliance Yes
§63.9(d) Special Compliance Requirement Notification Yes
§63.9(e) Notification of Performance Test Yes Applies only to capture system and add-on control device performance tests at sources using these to comply with the standards.
§63.9(f) Notification of Visible Emissions/Opacity Test No Subpart KKKK does not have opacity or visible emission standards.
§63.9(g) Additional Notifications When Using CMS No
§63.9(h)(1)-(3) Notification of Compliance Status Yes Section 63.3510 specifies the dates for submitting the notification of compliance status.
§63.9(h)(5)-(6) Clarifications Yes
§63.9(i) Adjustment of Submittal Deadlines Yes
§63.9(j) Change in Previous Information Yes
§63.10(a) Recordkeeping/Reporting—Applicability and General Information Yes
§63.10(b)(1) General Recordkeeping Requirements Yes Additional requirements are specified in §§63.3512 and 63.3513.
§63.10(b)(2)(i)-(ii) Recordkeeping of Occurrence and Duration of Startups and Shutdowns and of Failures to Meet Standards Yes before August 24, 2020, No on and after August 24, 2020 See §63.3512(i).
§63.10(b)(2)(iii) Recordkeeping Relevant to Maintenance of Air Pollution Control and Monitoring Equipment Yes
§63.10(b)(2)(iv)-(v) Actions Taken to Minimize Emissions During Startup, Shutdown, and Malfunction Yes before August 24, 2020, No on and after August 24, 2020 See §63.3512(i)(4) for a record of actions taken to minimize emissions duration a deviation from the standard.
§63.10(b)(2)(vi) Recordkeeping for CMS Malfunctions Yes before August 24, 2020, No on and after August 24, 2020 See §63.3512(i) for records of periods of deviation from the standard, including instances where a CMS is inoperative or out-of-control.
§63.10(b)(2) (vii)-(xii) Records Yes
§63.10(b)(2) (xiii) No
§63.10(b)(2) (xiv) Yes
§63.10(b)(3) Recordkeeping Requirements for Applicability Determinations Yes
§63.10(c)(1) Additional Recordkeeping Requirements for Sources with CMS Yes
§63.10(c)(5)-(6) Yes
§63.10(c)(7)-(8) Additional Recordkeeping Requirements for Sources with CMS No See §63.3512(i) for records of periods of deviation from the standard, including instances where a CMS is inoperative or out-of-control.
§63.10(c)(10)-(14) Additional Recordkeeping Requirements for Sources with CMS Yes
§63.10(c)(15) Records Regarding the Startup, Shutdown, and Malfunction Plan Yes before August 24, 2020, No on and after August 24, 2020
§63.10(d)(1) General Reporting Requirements Yes Additional requirements are specified in §63.3511.
§63.10(d)(2) Report of Performance Test Results Yes Additional requirements are specified in §63.3511(b).
§63.10(d)(3) Reporting Opacity or Visible Emissions Observations No Subpart KKKK does not require opacity or visible emissions observations.
§63.10(d)(4) Progress Reports for Sources with Compliance Extensions Yes
§63.10(d)(5) Startup, Shutdown, Malfunction Reports Yes before August 24, 2020, No on and after August 24, 2020 See §63.3511(a)(7) and (8).
§63.10(e)(1)-(2) Additional CMS Reports No
§63.10(e)(3) Excess Emissions/CMS Performance Reports No Section 63.3511(b) specifies the contents of periodic compliance reports.
§63.10(e)(4) COMS Data Reports No Subpart KKKK does not specify requirements for opacity or COMS.
§63.10(f) Recordkeeping/Reporting Waiver Yes
§63.11 Control Device Requirements/Flares No Subpart KKKK does not specify use of flares for compliance.
§63.12 State Authority and Delegations Yes
§63.13(a) Addresses Yes before August 24, 2020, No on and after August 24, 2020
§63.13(b) Submittal to State Agencies Yes
§63.13(c) Submittal to State Agencies Yes before August 24, 2020, No unless the state requires the submittal via CEDRI, on and after August 24, 2020
§63.14 Incorporation by Reference Yes
§63.15 Availability of Information/Confidentiality Yes

[85 FR 10856, Feb. 25, 2020]