Affected facilities at the following MWC sites | City, State | Increment 1 Submit final control plan |
Increment 2 Award contracts |
Increment 3 Begin on-site construction |
Increment 4 Complete on-site construction |
Increment 5 Final compliancec |
---|---|---|---|---|---|---|
Stanislaus Resource Recovery Facility | Crows Landing, California | January 11, 1999 | 01/19/00 | 05/19/00 | 11/19/00 | 12/19/00 |
Southeast Resource Recovery Facility | Long Beach, California | January 11, 1999 | 04/30/99 | 10/31/99 | 04/30/00 | 12/19/00 |
All large MWC units | Maine | January 11, 1999 | 01/01/99 | 07/01/99 | 09/01/00 | 12/19/00 |
Baltimore Resco | Baltimore, Maryland | January 11, 1999 | January 11, 1999 | January 11, 1999 | 09/01/00 | 12/19/00 |
All large MWC units | New Jerseyb | January 11, 1999 | 05/18/99 | 11/14/99 | 11/19/00 | 12/19/00 |
American Ref-Fuel | Delaware County, Pennsylvania | 11/01/98 | 05/18/99 | 11/14/99 | 11/19/00 | 12/19/00 |
Montenay Energy Resource | Montgomery County, Pennsylvania | 11/01/98 | 05/18/99 | 11/14/99 | 11/19/00 | 12/19/00 |
I-95 Energy/Resource Recovery Facility | Lorton, Virginia | January 11, 1999 | 10/15/99 | 03/01/00 | 11/19/00 | 12/19/00 |
New Hanover County, Unit 3A | Wilmington, North Carolina | 09/15/99 | 03/01/00 | 07/01/00 | 11/19/00 | 12/19/00 |
aThese schedules have been reviewed and determined to be acceptable by EPA.
bThis schedule applies to HC1 SO2, PM, Pb, Cd, CO, and NOX. However, owners and operators of large MWC units in New Jersey have the option of reserving the portion of their control plan that addresses NOX. Owners and operators must submit the reserved portion to EPA by December 15, 1999.
cThe owner or operator of an affected facility that began construction, modification, or reconstruction after June 26, 1987 must achieve final compliance with the mercury and dioxins/furans limits within 1 year after promulgation of subpart FFF (i.e., by 11/12/99) or 1 year after permit issuance. Permit issuance is issuance of a revised construction permit or revised operating permit if a permit modification is required to retrofit controls. Final compliance must be achieved no later than December 19, 2000, even if the date “1 year after permit issuance” exceeds December 19, 2000.
[63 FR 63202, Nov. 12, 1998; 64 FR 17219, Apr. 8, 1999, as amended at 65 FR 33469, May 24, 2000]