40 CFR Table 7
Applicability of General Provisions to Subpart PPPPP
June 9, 2020
As stated in 63.9365, you must comply with the General Provisions in §§63.1 through 63.15 that apply to you according to the following table:
Table 7 to Subpart PPPPP of Part 63—Applicability of General Provisions to Subpart PPPPP
[As stated in 63.9365, you must comply with the General Provisions in §§63.1 through 15 that apply to you according to the following table:]
Open Table
Citation | Subject | Applicable to subpart PPPPP | Explanation |
---|---|---|---|
§63.1(a)(1)-(12) | General Applicability | Yes | |
§63.1(b)(1)-(3) | Initial Applicability Determination | Yes | Applicability to subpart PPPPP is also specified in §63.9285. |
§63.1(c)(1) | Applicability After Standard Established | Yes | |
§63.1(c)(2) | Applicability of Permit Program for Area Sources | No | Area sources are not subject to subpart PPPPP. |
§63.1(c)(5) | Notifications | Yes | |
§63.1(d) | [Reserved] | ||
§63.1(e) | Applicability of Permit Program Before Relevant Standard is Set | Yes | |
§63.2 | Definitions | Yes | Additional definitions are specified in §63.9375. |
§63.3 | Units and Abbreviations | Yes | |
§63.4 | Prohibited Activities and Circumvention | Yes | |
§63.5(a) | Construction/Reconstruction | Yes | |
§63.5(b) | Requirements for Existing, Newly Constructed, and Reconstructed Sources | Yes | |
§63.5(d) | Application for Approval of Construction/Reconstruction | Yes | |
§63.5(e) | Approval of Construction/Reconstruction | Yes | |
§63.5(f) | Approval of Construction/Reconstruction based on Prior State Review | Yes | |
§63.6(a) | Compliance With Standards and Maintenance Requirements-Applicability | Yes | |
§63.6(b)(1)-(7) | Compliance Dates for New and Reconstructed Sources | Yes | §63.9295 specifies the compliance dates. |
§63.6(c)(1)-(2) | Compliance Dates for Existing Sources | No | Subpart PPPPP does not establish standards for existing sources. |
§63.6(c)(5) | Compliance Dates for Existing Sources | Yes | §63.9295(b) specifies the compliance date if a new or reconstructed area source becomes a major source. |
§63.6(e)(1)(i) | Operation and Maintenance | Yes before December 1, 2020. No on and after December 1, 2020 | See §63.9305 for general duty requirement. |
§63.6(e)(1)(ii) | Operation and Maintenance | Yes before December 1, 2020. No on and after December 1, 2020 | |
§63.6(e)(1)(iii) | Operation and Maintenance | Yes | |
§63.6(e)(3) | SSM Plan | Yes before December 1, 2020. No on and after December 1, 2020 | |
§63.6(f)(1) | Compliance Except During SSM | Yes before December 1, 2020. No on and after December 1, 2020 | |
§63.6(f)(2)-(3) | Methods for Determining Compliance | Yes | |
§63.6(g)(1)-(3) | Use of Alternative Standards | Yes | |
§63.6(h) | Compliance With Opacity/Visible Emission Standards | No | Subpart PPPPP does not establish opacity standards and does require continuous opacity monitoring systems (COMS). |
§63.6(i)(1)-(16) | Extension of Compliance | No | Compliance extension provisions apply to existing sources which do not have emission limitations in subpart PPPPP. |
§63.6(j) | Presidential Compliance Exemption | Yes | |
§63.7(a)(1)-(2) | Performance Test Dates | Yes | |
§63.7(a)(3) | Performance Test Required By the Administrator | Yes | |
§63.7(b)-(d) | Performance Test Requirements-Notification, Quality Assurance, Facilities Necessary for Safe Testing, Conditions During Testing | Yes | |
§63.7(e)(1) | Conditions for Conducting Performance Tests | Yes before December 1, 2020. No, see §63.9321, on and after December 1, 2020 | |
§63.7(e)(2)-(4) | Conduct of Performance Tests | Yes | |
§63.7(f) | Alternative Test Methods | Yes | |
§63.7(g)-(h) | Performance Testing Requirements-Data Analysis, Recordkeeping, Reporting, Waiver of Test | Yes | |
§63.8(a)(1)-(2) | Monitoring Requirements—Applicability | Yes | Subpart PPPPP contains specific requirement for monitoring at §63.9325. |
§63.8(a)(4) | Additional Monitoring Requirements | No | Subpart PPPPP does not have monitoring requirement for flares. |
§63.8(b) | Conduct of Monitoring | Yes | |
§63.8(c)(1) | Continuous Monitoring System (CMS) Operation and Maintenance | Yes | |
§63.8(c)(1)(i) | General Duty to Minimize Emissions and CMS Operation | Yes before December 1, 2020. No on and after December 1, 2020 | |
§63.8(c)(1)(ii) | Operation and Maintenance of CMS | Yes | |
§63.8(c)(1)(iii) | Requirement to Develop SSM Plan for CMS | Yes before December 1, 2020. No on and after December 1, 2020 | |
§63.8(c)(2)-(3) | Monitoring System Installation | Yes | |
§63.8(c)(4) | CMS | No | §63.9335(a) and (b) specifies the requirements. |
§63.8(c)(5) | COMS | No | Subpart PPPPP does not have opacity or VE standards. |
§63.8(c)(6)-(8) | CMS Requirements | Yes | Except that subpart PPPPP does not require COMS. |
§63.8(d)(1)-(2) | CMS Quality Control | Yes | |
§63.8(d)(3) | CMS Quality Control | Yes before December 1, 2020. No on and after December 1, 2020 | |
§63.8(e) | CMS Performance | Yes | Except for §63.8(e)(5)(ii) which applies to COMS. |
§63.8(f)(1)-(5) | Alternative Monitoring Method | Yes | |
§63.8(f)(6) | Alternative to Relative Accuracy Test | Yes | |
§63.8(g) | Data Reduction | Yes before December 1, 2020. No on and after December 1, 2020 | §§63.9335 and 63.9340 specify monitoring data reduction. |
§63.9(a)-(b) | Notification Requirements | Yes | |
§63.9(c) | Request for Compliance Extension | No | Compliance extension to not apply to new or reconstructed sources. |
§63.9(d) | Notification of Special Compliance Requirements for New Sources | Yes | |
§63.9(e) | Notification of Performance Test | No | Subpart PPPPP does not require performance testing. |
§63.9(f) | Notification of Opacity/VE test | No | Subpart PPPPP does not have opacity/VE standards. |
§63.9(g)(1) | Additional Notifications When Using CMS | Yes | |
§63.9(g)(2) | Additional Notifications When Using CMS | No | Subpart PPPPP does not have opacity/VE standards. |
§63.9(g)(3) | Additional Notifications When Using CMS | Yes | |
§63.9(h) | Notification of Compliance Status | Yes | |
§63.9(i) | Adjustment of Submittal Deadlines | Yes | |
§63.9(j) | Change in Previous Information | Yes | |
§63.10(a) | Recordkeeping/Reporting | Yes | |
§63.10(b)(1) | General Recordkeeping Requirements | Yes | |
§63.10(b)(2)(i) | Recordkeeping of Occurrence and Duration of Startups and Shutdowns | Yes before December 1, 2020. No on and after December 1, 2020 | |
§63.10(b)(2)(ii) | Recordkeeping of Occurrence and Duration of Malfunctions | Yes before December 1, 2020. No on and after December 1, 2020 | See §63.9355 for recordkeeping of (1) date, time, and duration; (2) listing of affected source or equipment, and an estimate of the quantity of each regulated pollutant emitted over the standard; and (3) actions to minimize emissions and correct the failure. |
§63.10(b)(2)(iii) | Recordkeeping of Maintenance on Controls and Monitoring Equipment | Yes | |
§63.10(b)(2)(iv)-(v) | Actions Taken to Minimize Emissions During SSM | Yes before December 1, 2020. No on and after December 1, 2020 | |
§63.10(b)(2)(vi)-(xi) | CMS Records | Yes | |
§63.10(b)(2)(xii) | Records | Yes | |
§63.10(b)(2)(xiii) | Records | Yes | |
§63.10(b)(2)(xiv) | Records | Yes | |
§63.10(b)(3) | Recordkeeping for Applicability Determinations | Yes | |
§63.10(c)(1)-(6), (9)-(14) | Additional Recordkeeping for CMS | Yes | |
§63.10(c)(7)-(8) | Records of Excess Emissions and Parameter Monitoring Exceedances for CMS | No | Specific language is located at §63.9355 of subpart PPPPP. |
§63.10(c)(15) | Records Regarding the SSM Plan | Yes before December 1, 2020. No on and after December 1, 2020 | |
§63.10(d)(1) | General Reporting Requirements | Yes | |
§63.10(d)(2) | Report of Performance Test Results | Yes | |
§63.10(d)(3) | Reporting of Opacity or VE Observations | No | Subpart PPPPP does not have opacity/VE standards. |
§63.10(d)(4) | Progress Reports for Sources with Compliance Extensions | No | Compliance extensions do not apply to new or reconstructed sources. |
§63.10(d)(5) | SSM Reports | Yes before December 1, 2020. No on and after December 1, 2020 | On and after December 1, 2020, see §63.9350 for malfunction reporting requirements. |
§63.10(e)(1) and (2)(i) | Additional CMS Reports | Yes | |
§63.10(e)(2)(ii) | Additional CMS Reports | No | Subpart PPPPP does not require COMS. |
§63.10(e)(3) | Excess Emissions/CMS Performance Reports | No | Specific language in located in §63.9350 of subpart PPPPP. |
§63.10(e)(4) | COMS Data Reports | No | Subpart PPPPP does not require COMS. |
§63.10(f) | Waiver for Recordkeeping/Reporting | Yes | |
§63.11 | Control Device Requirements/Flares | No | Subpart PPPPP does not specify use of flares for compliance. |
§63.12 | State Authority and Delegations | Yes | |
§63.13 | Addresses | Yes | |
§63.14 | Incorporation by Reference | Yes | ASTM D 6522-00 and ANSI/ASME PTC 19.10-1981 (incorporated by reference—See §63.14). |
§63.15 | Availability of Information/Confidentiality | Yes |
[85 FR 34349, June 3, 2020]