As required in §63.7140, you must comply with the applicable General Provisions requirements according to the following table:

Open Table
Citation Summary of requirement Am I subject to this requirement? Explanations
§63.1(a)(1)-(4) Applicability Yes
§63.1(a)(5) No
§63.1(a)(6) Applicability Yes
§63.1(a)(7)-(a)(9) No
§63.1(a)(10)-(a)(14) Applicability Yes
§63.1(b)(1) Initial Applicability Determination Yes §§63.7081 and 63.7142 specify additional applicability determination requirements.
§63.1(b)(2) No
§63.1(b)(3) Initial Applicability Determination Yes
§63.1(c)(1) Applicability After Standard Established Yes
§63.1(c)(2) Permit Requirements No Area sources not subject to subpart AAAAA, except all sources must make initial applicability determination.
§63.1(c)(3) No
§63.1(c)(4)-(5) Extensions, Notifications Yes
§63.1(d) No
§63.1(e) Applicability of Permit Program Yes
§63.2 Definitions Additional definitions in §63.7143.
§63.3(a)-(c) Units and Abbreviations Yes
§63.4(a)(1)-(a)(2) Prohibited Activities Yes
§3.4(a)(3)-(a)(5) No
§63.4(b)-(c) Circumvention, Severability Yes
§63.5(a)(1)-(2) Construction/Reconstruction Yes
§63.5(b)(1) Compliance Dates Yes
§63.5(b)(2) No
§63.5(b)(3)-(4) Construction Approval, Applicability Yes
§63.5(b)(5) No
§63.5(b)(6) Applicability Yes
§63.5(c) No
§63.5(d)(1)-(4) Approval of Construction/Reconstruction Yes
§63.5(e) Approval of Construction/Reconstruction Yes
§63.5(f)(1)-(2) Approval of Construction/Reconstruction Yes
§63.6(a) Compliance for Standards and Maintenance Yes
§63.6(b)(1)-(5) Compliance Dates Yes
§63.6(b)(6) No
§63.6(b)(7) Compliance Dates Yes
§63.6(c)(1)-(2) Compliance Dates Yes
§63.6(c)(3)-(c)(4) No
§63.6(c)(5) Compliance Dates Yes
§63.6(d) No
§63.6(e)(1) Operation & Maintenance Yes See §63.7100 for OM&M requirements.
§63.6(e)(2) No
§63.6(e)(3) Startup, Shutdown Malfunction Plan Yes
§63.6(f)(1)-(3) Compliance with Emission Standards Yes
§63.6(g)(1)-(g)(3) Alternative Standard Yes
§63.6(h)(1)-(2) Opacity/VE Standards Yes
§63.6(h)(3) No
§63.6(h)(4)-(h)(5)(i) Opacity/VE Standards Yes This requirement only applies to opacity and VE performance checks required in Table 4 to subpart AAAAA.
§63.6(h)(5) (ii)-(iii) Opacity/VE Standards No Test durations are specified in subpart AAAAA; subpart AAAAA takes precedence.
§63.6(h)(5)(iv) Opacity/VE Standards No
§63.6(h)(5)(v) Opacity/VE Standards Yes
§63.6(h)(6) Opacity/VE Standards Yes
§63.6(h)(7) COM Use Yes
§63.6(h)(8) Compliance with Opacity and VE Yes
§63.6(h)(9) Adjustment of Opacity Limit Yes
§63.6(i)(1)-(i)(14) Extension of Compliance Yes
§63.6(i)(15) No
§63.6(i)(16) Extension of Compliance Yes
§63.6(j) Exemption from Compliance Yes
§63.7(a)(1)-(a)(3) Performance Testing Requirements Yes §63.7110 specifies deadlines; §63.7112 has additional specific requirements.
§63.7(b) Notification Yes
§63.7(c) Quality Assurance/Test Plan Yes
§63.7(d) Testing Facilities Yes
§63.7(e)(1)-(4) Conduct of Tests Yes
§63.7(f) Alternative Test Method Yes
§63.7(g) Data Analysis Yes
§63.7(h) Waiver of Tests Yes
§63.8(a)(1) Monitoring Requirements Yes See §63.7113.
§63.8(a)(2) Monitoring Yes
§63.8(a)(3) No
§63.8(a)(4) Monitoring No Flares not applicable.
§63.8(b)(1)-(3) Conduct of Monitoring Yes
§63.8(c)(1)-(3) CMS Operation/Maintenance Yes
§63.8(c)(4) CMS Requirements No See §63.7121.
§63.8(c)(4)(i)-(ii) Cycle Time for COM and CEMS Yes No CEMS are required under subpart AAAAA; see §63.7113 for CPMS requirements.
§63.8(c)(5) Minimum COM procedures Yes COM not required.
§63.8(c)(6) CMS Requirements No See §63.7113.
§63.8(c)(7)-(8) CMS Requirements Yes
§63.8(d) Quality Control No See §63.7113.
§63.8(e) Performance Evaluation for CMS No
§63.8(f)(1)-(f)(5) Alternative Monitoring Method Yes
§63.8(f)(6) Alternative to Relative Accuracy test No
§63.8(g)(1)-(g)(5) Data Reduction; Data That Cannot Be Used No See data reduction requirements in §§63.7120 and 63.7121.
§63.9(a) Notification Requirements Yes See §63.7130.
§63.9(b) Initial Notifications Yes
§63.9(c) Request for Compliance Extension Yes
§63.9(d) New Source Notification for Special Compliance Requirements Yes
§63.9(e) Notification of Performance Test Yes
§63.9(f) Notification of VE/Opacity Test Yes This requirement only applies to opacity and VE performance tests required in Table 4 to subpart AAAAA. Notification not required for VE/opacity test under Table 6 to subpart AAAAA.
§63.9(g) Additional CMS Notifications No Not required for operating parameter monitoring.
§63.9(h)(1)-(h)(3) Notification of Compliance Status Yes
§63.9(h)(4) No
§63.9(h)(5)-(h)(6) Notification of Compliance Status Yes
§63.9(i) Adjustment of Deadlines Yes
§63.9(j) Change in Previous Information Yes
§63.10(a) Recordkeeping/Reporting General Requirements Yes See §§63.7131 through 63.7133.
§63.10(b)(1)-(b)(2)(xii) Records Yes
§63.10(b)(2)(xiii) Records for Relative Accuracy Test No
§63.10(b)(2)(xiv) Records for Notification Yes
§63.10(b)(3) Applicability Determinations Yes
§63.10(c) Additional CMS Recordkeeping No See §63.7132.
§63.10(d)(1) General Reporting Requirements Yes
§63.10(d)(2) Performance Test Results Yes
§63.10(d)(3) Opacity or VE Observations Yes For the periodic monitoring requirements in Table 6 to subpart AAAAA, report according to §63.10(d)(3) only if VE observed and subsequent visual opacity test is required.
§63.10(d)(4) Progress Reports Yes
§63.10(d)(5) Startup, Shutdown, Malfunction Reports Yes
§63.10(e) Additional CMS Reports No See specific requirements in subpart AAAAA, see §63.7131.
§63.10(f) Waiver for Recordkeeping/Reporting Yes
§63.11(a)-(b) Control Device Requirements No Flares not applicable.
§63.12(a)-(c) State Authority and Delegations Yes
§63.13(a)-(c) State/Regional Addresses Yes
§63.14(a)-(b) Incorporation by Reference No
§63.15(a)-(b) Availability of Information Yes