Each State must submit a HIT PAPD update or a HIT IAPD no later than 60 days after the occurrence of project changes including but not limited to any of the following:

(a) A projected cost increase of $100,000 or more.

(b) A schedule extension of more than 60 days for major milestones.

(c) A significant change in planning approach or implementation approach, or scope of activities beyond that approved in the HIT planning advance planning document or the HIT implementation advance planning document.

(d) A change in implementation concept or a change to the scope of the project.

(e) A change to the approved cost allocation methodology.