(a) Definitions
In this section:

(1) Eligible entity
The term "eligible entity" means—

(A) a utility;

(B) an electric cooperative;

(C) a State;

(D) a political subdivision of a State;

(E) an Indian tribe; or

(F) a Native corporation.

(2) High-cost region
The term "high-cost region" means a region in which the average cost of electrical power exceeds 150 percent of the national average retail cost, as determined by the Secretary.

(b) Program
The Secretary shall use amounts made available to carry out this section to make grants to eligible entities for activities described in subsection (c).

(c) Eligible activities
An eligible entity may use grant funds under this section, with respect to a geothermal energy project in a high-cost region, only—

(1) to conduct a feasibility study, including a study of exploration, geochemical testing, geomagnetic surveys, geologic information gathering, baseline environmental studies, well drilling, resource characterization, permitting, and economic analysis;

(2) for design and engineering costs, relating to the project; and

(3) to demonstrate and promote commercial application of technologies related to geothermal energy as part of the project.

(d) Cost sharing
The cost-sharing requirements of section 16352 of this title shall apply to any project carried out under this section.

(e) Authorization of appropriations
There are authorized to be appropriated such sums as are necessary to carry out this section.

Effective Date

Section effective on the date that is 1 day after Dec. 19, 2007, see section 1601 of Pub. L. 110–140, set out as a note under section 1824 of Title 2, The Congress.


Tried the LawStack mobile app?

Join thousands and try LawStack mobile for FREE today.

  • Carry the law offline, wherever you go.
  • Download CFR, USC, rules, and state law to your mobile device.