In addition to the regular monthly report information required by §3276.12, send to BLM:
(a) Steam flow into the turbine in klbs; for dual flash facilities, you must separate the steam flow into high pressure steam and low pressure steam;
(b) Condenser pressure in psia;
(c) Condenser temperature in deg. F;
(d) Auxiliary steam flow used for gas ejectors, steam seals, pumps, etc., in klbs;
(e) Flow of condensate out of the plant (after the cooling towers) in klbs; and
(f) Any other information we may require.