(a) BLM will approve the unit area designation in writing and notify the prospective unit operator once we determine that:

(1) We have received the information required at §3281.2;

(2) Information available to BLM documents that the area is geologically appropriate for unitization; and

(3) Unitization is appropriate to conserve the natural resources of a geothermal reservoir, field, or like area, or part thereof.

(b) BLM will notify a prospective unit operator in writing if we do not designate a proposed unit area.