43 CFR § 404.37
How will Reclamation determine the appropriate non-Federal share of construction costs?
June 11, 2020
Reclamation will determine the appropriate non-Federal share of construction costs in the process of developing the feasibility report. The non-Federal cost-share will be:
(a) At least 25 percent of the total construction costs; and
(b) An additional amount based on your capability to pay, as appropriate, to be determined by Reclamation based on the factors in §404.39.