43 CFR § 4300.23
After I file my application, can I use the land before BLM issues my permit?
June 11, 2020
No. You cannot use the land until BLM issues you a permit. Generally, BLM will issue a permit within 120 days after receiving an application and will keep you informed if there are delays in meeting that timeframe.