The CO shall prepare the Schedule as follows:
(a) Section A, Solicitation/contract form. Use SF 1442, Solicitation, Offer, and Award (Construction, Alteration or Repair), as prescribed in FAR 36.701(a).
(b) Section B, Bid schedule. Bid schedule.
(c) Section C, Specifications/Drawings. Include specifications and drawings (See FAR Part 11) or reference other location in the uniform contract format (e.g. Section J, attachment ___).
(d) Section D, Packaging and Marking. Not applicable.
(e) Section E, Inspection and acceptance. Include inspection, acceptance, quality assurance, and reliability requirements (See FAR Part 46).
(f) Section F, Deliveries or performance. Include Suspension of Work, Liquidated Damages, Commencement, Prosecution, and Completion of Work, Variation in Quantity clauses (See FAR Part 12).
(g) Section G, Contract administration data. Include Contracting Officer's Representative/Technical Representative identification, and any required administration information (e.g., accounting and appropriation data).
(h) Section H, Special contract requirements. Include any special contract requirements which are not included in other sections of the uniform contract format.