(a) The contracting officer shall insert the clause at 52.217-2, Cancellation Under Multiyear Contracts, in solicitations and contracts when a multiyear contract is contemplated.
(b) Economic price adjustment clauses. Economic price adjustment clauses are adaptable to multiyear contracting needs. When the period of production is likely to warrant a labor and material costs contingency in the contract price, the contracting officer should normally use an economic price adjustment clause (see 16.203). When contracting for services, the contracting officer—
(1) Shall add the clause at 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards—Price Adjustment (Multiple Year and Option Contracts), when the contract includes the clause at 52.222-41, Service Contract Labor Standards;
(2) May modify the clause at 52.222-43 in overseas contracts when laws, regulations, or international agreements require contractors to pay higher wage rates; or
(3) May use an economic price adjustment clause authorized by 16.203, when potential fluctuations require coverage and are not included in cost contingencies provided for by the clause at 52.222-43.
[61 FR 39204, July 26, 1996, as amended at 72 FR 63078, Nov. 7, 2007; 79 FR 24202, Apr. 29, 2014]