(1) Use the clause at 252.215-7002, Cost Estimating System requirements, in all solicitations and contracts to be awarded on the basis of certified cost or pricing data.
(2) When contracting with the Canadian Commercial Corporation—
(i)
(A) Use the provision at 252.215-7003, Requirement for Submission of Data Other Than Certified Cost or Pricing Data—Canadian Commercial Corporation—
(1) In lieu of DFARS 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, in a solicitation, including solicitations using FAR part 12 procedures for the acquisition of commercial items, for a sole source acquisition from the Canadian Commercial Corporation that is—
(i) Cost-reimbursement, if the contract value is expected to exceed $700,000; or
(ii) Fixed-price, if the contract value is expected to exceed $500 million; or
(2) In lieu of DFARS 252.215-7010, in a solicitation, including solicitations using FAR part 12 procedures for the acquisition of commercial items, for a sole source acquisition from the Canadian Commercial Corporation that does not meet the thresholds specified in paragraph (2)(i)(A)(1) of this section, if approval is obtained as required at 225.870-4(c)(2)(ii); and
(B) Do not use 252.225-7003 in lieu of DFARS 252.215-7010 in competitive acquisitions; and
(ii)
(A) Use the clause at 252.215-7004, Requirement for Submission of Data Other Than Certified Cost or Pricing Data—Modifications—Canadian Commercial Corporation—
(1) In a solicitation, including solicitations using FAR part 12 procedures for the acquisition of commercial items, for a sole source acquisition, from the Canadian Commercial Corporation and resultant contract that is—
(i) Cost-reimbursement, if the contract value is expected to exceed $700,000; or
(ii) Fixed-price, if the contract value is expected to exceed $500 million;
(2) In a solicitation, including solicitations using FAR part 12 procedures for the acquisition of commercial items, for a sole source acquisition from the Canadian Commercial Corporation and resultant contract that does not meet the thresholds specified in paragraph (2)(ii)(A)(1) of this section, if approval is obtained as required at 225.870-4(c)(2)(ii); or
(3)(i) In a solicitation, including solicitations using FAR part 12 procedures for the acquisition of commercial items, for a competitive acquisition that includes FAR 52.215-21, Requirement for Data Other Than Certified Cost or Pricing Data—Modifications, or that meets the thresholds specified in paragraph (2)(ii)(A)(1) of this section.
(ii) The contracting officer shall then select the appropriate clause to include in the contract (52.215-21 only if award is not to the Canadian Commercial Corporation; or 252.215-7004 if award is to the Canadian Commercial Corporation and necessary approval is obtained in accordance with 225.870-4(c)(2)(ii)); and
(B) The contracting officer may specify a higher threshold in paragraph (b) of the clause 252.215-7004.
(3) Use the provision at 252.215-7008, Only One Offer, in competitive solicitations that exceed the simplified acquisition threshold, including solicitations using FAR part 12 procedures for the acquisition of commercial items.
(4) When the solicitation requires the submission of certified cost or pricing data, the contracting officer should include 252.215-7009, Proposal Adequacy Checklist, in the solicitation to facilitate submission of a thorough, accurate, and complete proposal.
(5) When reasonably certain that the submission of certified cost or pricing data or data other than certified cost or pricing data will be required or when using the provision at 252.215-7008—
(i) Use the basic or alternate of the provision at 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, in lieu of the provision at FAR 52.215-20, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, in solicitations, including solicitations using FAR part 12 procedures for the acquisition of commercial items.
(A) Use the basic provision when submission of certified cost or pricing data is required to be in the FAR Table 15-2 format, or if it is anticipated, at the time of solicitation, that the submission of certified cost or pricing data may not be required.
(B) Use the alternate I provision to specify a format for certified cost or pricing data other than the format required by FAR Table 15-2;
(ii) Use the provision at 252.215-7011, Requirements for Submission of Proposals to the Administrative Contracting Officer and Contract Auditor, when using the basic or alternate of the provision at 252.215-7010 and copies of the proposal are to be sent to the ACO and contract auditor; and
(iii) Use the provision at 252.215-7012, Requirements for Submission of Proposals via Electronic Media, when using the basic or alternate of the provision at 252.215-7010 and submission via electronic media is required.
(6) Use the provision at 252.215-7013, Supplies and Services Provided by Nontraditional Defense Contractors, in all solicitations.
(7) Use the clause at 252.215-7014, Exception from Certified Cost or Pricing Data Requirements for Foreign Military Sales Indirect Offsets, in solicitations and contracts that contain the provision at 252.215-7010, Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data, when it is reasonably certain that—
(i) The contract is expected to include costs associated with an indirect offset; and
(ii) The submission of certified cost or pricing data or data other than certified cost or pricing data will be required.
(8) Use the clause at 252.215-7015, Program Should-Cost Review, in all solicitations and contracts for the development or production of a major weapon system, as defined in 234.7001.
[63 FR 55040, Oct. 14, 1998, as amended at 72 FR 20760, Apr. 26, 2007; 73 FR 27472, May 13, 2008; 75 FR 48279, Aug. 10, 2010; 77 FR 39139, June 29, 2012; 77 FR 43472, July 24, 2012; 77 FR 76940, Dec. 31, 2012; 78 FR 13543, Feb. 28, 2013; 78 FR 18872, Mar. 28, 2013; 78 FR 37986, June 25, 2013; 78 FR 65216, Oct. 31, 2013; 81 FR 28730, May 10, 2016; 81 FR 36473, June 7, 2016; 83 FR 4444, Jan. 31, 2018; 83 FR 30825, 30828, June 29, 2018; 84 FR 30949, June 28, 2019; 84 FR 65309, Nov. 27, 2019]